On the map
State significant development

Yiribana Logistics Estate

Decided: approved on 22 Sep 2023Industry and warehouses

Where it is in the process

Approved on 22 Sep 2023

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination22 Sep 2023 (done)
  9. Approved22 Sep 2023

What it proposes

The department's description

Concept plan and Stage 1 DA for an industrial estate. Stage 1 comprises two warehouses, site-wide bulk earthworks and retaining walls, an internal road network, storm water works, car parking, signage and landscaping.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

5 submissions: 1 from the public, 3 from organisations and 1 from public authorities

Object0
Support0
Comment5

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

3 changes to the project after its decision, each assessed as a case of its own, newest first.

Yiribana Logistics Estate MOD 3 - Warehouse 3 Design ChangesSSD-10272349-Mod-3

Decided: approved on 18 Nov 2026 by the department (team leader)

Modifications to the design of Warehouse 3 to accommodate changes to the approved internal layout, built form, loading dock and driveway arrangements to meet tenant operational requirements, including introduction of a click-and-collect operation.

Its 20 documents

20 documents in 5 folders, each on the NSW Planning Portal

Modification Application11

See the 11 documents on the Planning Portal

Agency Advice2

See the 2 documents on the Planning Portal

Additional Information4

See the 4 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Yiribana Logistics Estate MOD 2 – Civil Works AmendmentsSSD-10272349-Mod-2

Under way: at assessment

The modification proposes changes to the estate road layout, additional bulk earthworks, and revised stormwater infrastructure and retaining walls, without changing the approved land use, warehouse layout, gross floor area or parking.

Its 21 documents

21 documents in 3 folders, each on the NSW Planning Portal

Modification Application15

See the 15 documents on the Planning Portal

Agency Advice5

See the 5 documents on the Planning Portal

Additional Information1

See the document on the Planning Portal

Its page on the Planning Portal

Yiribana Estate (GPT) MOD 1 - Retaining WallSSD-10272349-Mod-1

Decided: approved on 22 Aug 2025 by the department (team leader)

The purpose of this Modification Application (Mod 1) is to amend the proposal with respect to a minor change associated with the location of a retaining wall (Retaining Wall 2) which flanks the northern boundary of Lot 2.

Its 16 documents

16 documents in 5 folders, each on the NSW Planning Portal

Modification Application5

See the 5 documents on the Planning Portal

Agency Advice3

See the 3 documents on the Planning Portal

Additional Information5

See the 5 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

241 documents in 13 folders, each on the NSW Planning Portal

Notice of Exhibition1
Request for SEARs1
SEARs3
EIS68
Response to Submissions31
Agency Advice35
Amendments2
Additional Information47
Determination3
Management Plans and Strategies38
Reports4
Notifications6
Other Documents2

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 19 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.