Aspect Industrial Estate Stage 3 Development (Warehouse 2)

Decided: approved on 5 Jul 2024Industry and warehouses

Where it is in the process

Approved on 5 Jul 2024

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination5 Jul 2024 (done)
  9. Approved5 Jul 2024

What it proposes

The department's description

Construction and operation of a warehouse and distribution facility

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

8 submissions: 3 from organisations and 5 from public authorities

Object0
Support0
Comment8

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

3 changes to the project after its decision, each assessed as a case of its own, newest first.

Aspect Industrial Estate Stage 3 (WH2) Modification 3SSD-58257960-Mod-3

Decided: approved on 6 May 2026 by the department (team leader)

Modify the cumulative stormwater management strategy to align with the Water Management Strategy that has been established for the EEP Stage 1A SSDA.

Its 3 documents

3 documents in 2 folders, each on the NSW Planning Portal

Determination2
Consolidated Consent1

Its page on the Planning Portal

Aspect Warehouse 2 MOD 2 - Internal AdditionsSSD-58257960-Mod-2

Decided: approved on 16 Oct 2025 by the department (team leader)

Inclusion of a temperature controlled facility Increase roofline and propose rooftop plant Delete internal staircase to mezzanine office

Its 20 documents

Its page on the Planning Portal

Aspect Warehouse 2 MOD 1 - Stormwater ChangesSSD-58257960-Mod-1

Decided: approved on 7 May 2025 by the department (team leader)

Removal of 5 hectares of land within the EEP Site from the cumulative stormwater management strategy approved under the AIE Concept Plan Approval.

Its 15 documents

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

110 documents in 13 folders, each on the NSW Planning Portal

Notice of Exhibition1
Early Consultation3
Request for SEARs2
SEARs3
EIS34
Response to Submissions7
Agency Advice13
Additional Information10
Determination3
Management Plans and Strategies17
Reports3
Notifications4
Other Documents10

What's near it

Its point is approximate (the register's own, to about a kilometre), and so are these.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.