State significant development

Aspect Industrial Estate Stage 2 Development (Warehouse 9)

Decided: approved on 2 Mar 2023Industry and warehouses

Where it is in the process

Approved on 2 Mar 2023

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination2 Mar 2023 (done)
  9. Approved2 Mar 2023

What it proposes

The department's description

Construction and operation of Warehouse 9 of the Aspect Industrial Estate. The proposed warehouse would have a total GFA of 66,341 sqm with associated offices, loading docks, hardstands, car parks, landscaping, services and utilities.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

2 submissions: 1 from organisations and 1 from public authorities

Object0
Support0
Comment2

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

4 changes to the project after its decision, each assessed as a case of its own, newest first.

Aspect Industrial Estate - Stage 2 (WH9) MOD 4SSD-46516461-Mod-4

Decided: approved on 6 May 2026 by the department (team leader)

Modify the cumulative stormwater management strategy to align with the Water Management Strategy that has been established for the EEP Stage 1A SSDA.

Its 3 documents

3 documents in 2 folders, each on the NSW Planning Portal

Determination2
Consolidated Consent1

Its page on the Planning Portal

AIE Warehouse 9 MOD 3 - Stormwater ChangesSSD-46516461-Mod-3

Decided: approved on 7 May 2025 by the department (team leader)

A change removing 5 ha of land from the stormwater strategy for Aspect Industrial Estate Warehouse 9, Kemps Creek, approved on 7 May 2025.

The department's description

Removal of 5 hectares of land within the EEP Site from the cumulative stormwater management strategy approved under the AIE Concept Plan Approval.

Its 16 documents

Its page on the Planning Portal

AIE Warehouse 9 MOD 1 - Stormwater ManagementSSD-46516461-Mod-1

Decided: approved on 23 Jul 2024 by the department (team leader)

Modification to update the stormwater management approach for AIE stage 2

Its 18 documents

Its page on the Planning Portal

AIE Warehouse 9 MOD 2 - Temporary AccessSSD-46516461-Mod-2

Decided: approved on 15 Jul 2024 by the department (team leader)

Modification to enable temporary access for operational vehicles associated with Warehouse 9 to be facilitated over two phased.

Its 10 documents

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

160 documents in 11 folders, each on the NSW Planning Portal

Notice of Exhibition1
Request for SEARs3
SEARs1
EIS29
Response to Submissions19
Agency Advice21
Additional Information28
Determination3
Management Plans and Strategies37
Notifications6
Other Documents12

What's near it

Its point is approximate (the register's own, to about a kilometre), and so are these.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.