On the map
State significant development

Kemps Creek Data Centre

Decided: approved on 13 Jul 2023Industry and warehouses

Where it is in the process

Approved on 13 Jul 2023

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination13 Jul 2023 (done)
  9. Approved13 Jul 2023

What it proposes

The department's description

Construction and Operation of a Data Centre including two data storage buildings, 61 generators, substation, high voltage switch yard, 30 diesel storage tanks, office, internal access roads and landscaping.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

1 submission: 1 from public authorities

Object0
Support0
Comment1

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

1 change to the project after its decision, each assessed as a case of its own, newest first.

Kemps Creek Data Centre MOD 1 - Data Hall Fit-OutSSD-10101987-Mod-1

Decided: approved on 18 Nov 2024 by the department (team leader)

The modification seeks approval to undertake fit-out of the development's data halls with computing equipment.

Its 8 documents

8 documents in 4 folders, each on the NSW Planning Portal

Modification Application3

See the 3 documents on the Planning Portal

Agency Advice1

See the document on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.