State significant development

Aspect Industrial Estate Stage 4 Development (Warehouse 8)

Decided: approved on 11 Oct 2024Industry and warehouses

Where it is in the process

Approved on 11 Oct 2024

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination11 Oct 2024 (done)
  9. Approved11 Oct 2024

What it proposes

The department's description

Construction and operation of a warehouse and distribution centre.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

10 submissions: 3 from organisations and 7 from public authorities

Object0
Support0
Comment10

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

3 changes to the project after its decision, each assessed as a case of its own, newest first.

Aspect Industrial Estate Stage 4 (WH8) - Modification 3SSD-60513208-Mod-3

Decided: approved on 6 May 2026 by the department (team leader)

Modify the cumulative stormwater management strategy to align with the Water Management Strategy that has been established for the EEP Stage 1A SSDA.

Its 9 documents

Its page on the Planning Portal

AIE Warehouse 8 MOD 2 - Layout ChangesSSD-60513208-Mod-2

Decided: approved on 27 Jun 2025 by the department (executive director)

Modification to the Stage 4 Detailed Development, including amendments to Warehouse 8 layout.

Its 36 documents

Its page on the Planning Portal

AIE Warehouse 8 MOD 1 - Stormwater ChangesSSD-60513208-Mod-1

Decided: approved on 7 May 2025 by the department (team leader)

Removal of 5 hectares of land within the EEP Site from the cumulative stormwater management strategy approved under the AIE Concept Plan Approval.

Its 15 documents

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

133 documents in 12 folders, each on the NSW Planning Portal

Notice of Exhibition1
Request for SEARs6
SEARs2
EIS28
Response to Submissions27
Agency Advice11
Additional Information14
Determination2
Management Plans and Strategies30
Reports1
Notifications3
Other Documents8

What's near it

Its point is approximate (the register's own, to about a kilometre), and so are these.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.