On the map
State significant development

Hanworth Battery Energy Storage System

A 1.2 GW battery on Hanworth Road, Bannaby

Under way: at exhibitionEnergy: batteriesRegional scale

Where it is in the process

At exhibition, since 19 Nov 2026

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition19 Nov 2026 (current stage)
  4. Collate Submissions (to come)
  5. Response to Submissions (to come)
  6. Assessment (to come)
  7. Recommendation (to come)
  8. Determination (to come)

Open for comment until 17 Dec 2026. Anyone can make a submission on its page on the Planning Portal.

What it proposes

AI summary. Written from this project's page and its Scoping Report on the NSW Planning Portal, on 19 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

Out of date. This summary was written when the project was at Prepare EIS (summarised 19 Nov 2026); it has since moved to Exhibition.

A 1.2 GW battery on Hanworth Road, Bannaby

The proponent proposes a battery energy storage system with a capacity of about 1.2 GW and 4.8 GWh of storage at 576 Hanworth Road, Bannaby, in the Upper Lachlan Shire. It would sit on about 47.70 ha of rural land, with an onsite switching station and a transmission line of about 1.5 km to the neighbouring 330 kV Transgrid substation. The project would also include access roads, cabling and an upgraded existing building for operational staff. No capital investment or job numbers are stated.

The case is at the stage where the proponent prepares its environmental impact statement (EIS). The Secretary's environmental assessment requirements (SEARs) have been issued, and agencies have given advice on them. An EIS file is already listed with the case. No submissions have been received. Next, the EIS is exhibited for public comment, the proponent responds to the submissions, and the department then assesses the project.

Battery power capacity
1.2 GWScoping Report
Battery storage capacity
4.8 GWhScoping Report
Site area
47.7 haScoping Report
Transmission corridor length
1.5 kmScoping Report

The department's description

Construction, operation, and decommissioning of a battery energy storage system (BESS) with a capacity of 1.2GW/4.8GWh and ancillary infrastructure.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 19 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.