On the map
State significant development

Wattle Creek Solar Farm

A 265 MW solar farm and battery at Brayton, Upper Lachlan

Under way: at response to submissionsEnergy: solarDistrict scale

Where it is in the process

At response to submissions

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (current stage)
  6. Assessment (to come)
  7. Recommendation (to come)
  8. Determination (to come)

What it proposes

AI summary. Written from this project's page and its Environmental Impact Statement on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

A 265 MW solar farm and battery at Brayton, Upper Lachlan

The proponent proposes a hybrid solar farm of up to 265 MW with a 100 MW battery energy storage system, at 1001 Canyonleigh Road, Brayton, in the Upper Lachlan Shire. It is about 15 km north-west of Marulan, on a University of Sydney property. It would use about 490,000 solar panels and an on-site substation linked to Marulan Substation by overhead transmission line. A separate 350 MW battery is assessed under its own application. The environmental impact statement (EIS) gives a capital investment of about $543 million.

The EIS is dated March 2025. It has been exhibited and drew 84 submissions: 71 objecting, 8 supporting and 5 commenting. The case is now at the response to submissions stage, where the proponent answers the submissions and may amend the project. The department then assesses it and prepares an assessment report, and a decision-maker determines it. No decision has been made.

Solar farm capacity
265 MWEnvironmental Impact Statement
Capital investment
$543MEnvironmental Impact Statement
Battery capacity with the solar farm
100 MWEnvironmental Impact Statement
Solar panels
490,000 panelsEnvironmental Impact Statement
Separate battery capacity
350 MWEnvironmental Impact Statement
Households powered
55,000 householdsEnvironmental Impact Statement
Aboriginal archaeological sites impacted
14 sitesEnvironmental Impact Statement

The department's description

Development of a 265 MW solar farm with energy storage and associated infrastructure.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

84 submissions: 68 from the public, 15 from organisations and 1 from public authorities

Object71
Support8
Comment5

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

61 documents in 6 folders, each on the NSW Planning Portal

Notice of Exhibition1
Request for SEARs4
SEARs2
EIS25
Response to Submissions1
Agency Advice28

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.