On the map
Part 4 development

Taralga Wind

Decided: decidedEnergy: wind

Where it is in the process

At determination

  1. Prepare Scoping Report (done)
  2. SEARs (done)
  3. Prepare EIS (done)
  4. Exhibition (done)
  5. Collate Submissions (done)
  6. Response to Submissions (done)
  7. Assessment (done)
  8. Recommendation (done)
  9. Determination (current stage)

What it proposes

The portal gives no description.

Modifications

8 changes to the project after its decision, each assessed as a case of its own, newest first.

Mod 1 - Increase Turbine HeightDA241/04-Mod-1

Decided: approved by the department (executive director)

Its 13 documents

13 documents in 3 folders, each on the NSW Planning Portal

Application4

See the 4 documents on the Planning Portal

EA7

See the 7 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Its page on the Planning Portal

Mod 8 - Cooranbong Distribution ProjectDA241/04-Mod-8

Decided: approved on 14 Sep 2015 by the department (executive director)

Its 5 documents

5 documents in 3 folders, each on the NSW Planning Portal

Application1

See the document on the Planning Portal

EA1

See the document on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Its page on the Planning Portal

Mod 7 - Underground CablingDA241/04-Mod-7

Decided: approved on 13 Mar 2015 by the department (executive director)

Its 15 documents

15 documents in 2 folders, each on the NSW Planning Portal

Application7

See the 7 documents on the Planning Portal

Determination8

See the 8 documents on the Planning Portal

Its page on the Planning Portal

Mod 5 - Five Modification ElementsDA241/04-Mod-5

Decided: approved on 11 Nov 2014 by the department (executive director)

Its 15 documents

15 documents in 3 folders, each on the NSW Planning Portal

Application12

See the 12 documents on the Planning Portal

Response to Submissions1

See the document on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Its page on the Planning Portal

Mod 6 - Change to Heavy Vehicle RouteDA241/04-Mod-6

Decided: approved with conditions on 20 Jun 2014 by Dir(MIA)

Its 4 documents

4 documents in 2 folders, each on the NSW Planning Portal

Application2

See the 2 documents on the Planning Portal

Recommendation2

See the 2 documents on the Planning Portal

Its page on the Planning Portal

Mod 4 - Met MastsDA241/04-Mod-4

Decided: approved on 6 Nov 2013 by the department (director)

Its 8 documents

8 documents in 4 folders, each on the NSW Planning Portal

Application3

See the 3 documents on the Planning Portal

EA1

See the document on the Planning Portal

Response to Submissions2

See the 2 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Its page on the Planning Portal

Mod 3 - Change to site compoundsDA241/04-Mod-3

Decided: approved on 6 Nov 2013 by the department (director)

Its 8 documents

8 documents in 3 folders, each on the NSW Planning Portal

Application3

See the 3 documents on the Planning Portal

Response to Submissions3

See the 3 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Its page on the Planning Portal

Mod 1 - Reduction in TurbinesDA241/04-Mod-2

Decided: approved on 18 Jun 2013 by the department (executive director)

Its 10 documents

10 documents in 3 folders, each on the NSW Planning Portal

Application6

See the 6 documents on the Planning Portal

Recommendation2

See the 2 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

33 documents in 4 folders, each on the NSW Planning Portal

Determination11

See the 11 documents on the Planning Portal

Management Plans and Strategies19

See the 19 documents on the Planning Portal

Reports2

See the 2 documents on the Planning Portal

Other Documents1

See the document on the Planning Portal

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.