On the map
State significant development

Crookwell 3 Wind Farm

Decided: approved on 14 Oct 2020Energy: wind

Where it is in the process

Approved on 14 Oct 2020

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination14 Oct 2020 (done)
  9. Approved14 Oct 2020

What it proposes

The department's description

Development of a wind farm with up to 16 wind turbines and associated infrastructure.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

128 submissions: 110 from the public and 18 from organisations

Object44
Support62
Comment22

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

1 change to the project after its decision, each assessed as a case of its own, newest first.

MOD 1 - Biodiversity Offset ExtensionSSD-6695-Mod-1

Withdrawn: withdrawn

Extension of timeframe for finalising the delivery of required biodiversity offsets.

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.