Summit at Kemps Creek warehouse estate, Mamre Road
The project is a warehouse estate at 706-752 Mamre Road, Kemps Creek, in the Penrith council area, on a site of 52 ha. It is a concept proposal for eight buildings with 244,809 m² of gross floor area, plus a Stage 1 application for three buildings with 79,888 m² of floor area, site-wide earthworks and roads. It includes part of the Southern Link Road. The department gives a capital investment of $489 million for the concept proposal and 1,716 operational jobs.
The application was exhibited from 19 Mar 2024 to 15 Apr 2024, and the amended application from 11 Feb 2025 to 10 Mar 2025. The portal counts 7 submissions, all comments. The department recommended approval, and its Executive Director, as the Minister's delegate, approved it on 20 Feb 2026 with conditions. Next, the proponent must meet those conditions, and the later buildings need their own applications.
- Capital investment (concept proposal)
- $489MSSD-30628110 Assessment Report
- Concept proposal floor area
- 244,809 m²SSD-30628110 Assessment Report
- Stage 1 floor area
- 79,888 m²SSD-30628110 Assessment Report
- Operational jobs (concept proposal)
- 1,716 jobsSSD-30628110 Assessment Report
- Construction jobs (concept proposal)
- 1,981 jobsSSD-30628110 Assessment Report
- Stage 1 capital investment
- $235MSSD-30628110 Assessment Report
- Site area
- 52 haSSD-30628110 Assessment Report
- Concept proposal buildings
- 8 buildingsSSD-30628110 Assessment Report
The department's description
A Concept Proposal comprising nine buildings with a total gross floor area (GFA) of up to 244,413 square metres (m2) and Stage 1 development of three buildings with a total GFA of 79,263 m2.
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0
Submissions
What the public, organisations and public authorities said, counted by where they stood.
7 submissions: 6 from organisations and 1 from public authorities
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal
Documents
By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.
151 documents in 9 folders, each on the NSW Planning Portal
Notice of Exhibition2
Request for SEARs2
SEARs4
EIS50
- 24-03-13 - Response to RFI
- Appendix A - SEARs Compliance Table
- Appendix AA - Weed Eradication and Management Plan
- Appendix B - Architectural Drawings
- Appendix BB - Construction Environmental Management Plan
- Appendix C - Statutory Compliance Table
- Appendix CC - Social and Economic Impact Assessment
- Appendix D - Community Engagement Table
- Appendix DD - ESD Report
- Appendix E - Consolidated Mitigation Measures
- Appendix EE - Air Quality Impact Assessment
- Appendix F - CIV Cost Summary Report
- Appendix FF - Waste and Resource Management Plan
- Appendix G - Detailed Survey
- Appendix GG - Detailed Site Investigation
- Appendix H - Design Statement_
- Appendix HH - Remedial Action Plan
- Appendix I - Civil Infrastructure Report
- Appendix II - Bush Fire Assessment Report
- Appendix J - Water & Stormwater Management Plan
- Appendix JJ - Hazard and Risk Assessment
- Appendix K1 - Civil Drawings
- Appendix K2 - LOG-N Roadworks Civil Drawings
- Appendix KK - Aeronautical Impact Assessment
- Appendix L - Landscape Drawings
- Appendix LL1 - BCA 2022 Assessment Report
- Appendix LL2 - BCA 2022 Accessibility Report
- Appendix M - Plan of Proposed Subdivision
- Appendix MM - East-West Collector Road Coordination
- Appendix N - Mamre Road Precinct DCP Compliance Table
- Appendix NN - Trunk Drainage Realignment Correspondence
- Appendix O - Crime Prevention Through Environmental Design
- Appendix P - Community and Stakeholder Outcomes
- Appendix Q - Transport Management & Accessibility Plan_
- Appendix R - Detailed Geotechnical Investigation
- Appendix S - Salinity Management Plan
- Appendix T1 - Flood Impact Assessment
- Appendix T2 - Flood Impact Assessment Addendum
- Appendix U - Visual Impact Assessment Report
- Appendix V - Noise Impact Assessment
- Appendix W - Aboriginal Cultural Heritage Assessment
- Appendix X - Archaeological Report
- Appendix Y - Historical Heritage Impact Assessment
- Appendix Z - Biodiversity Development Assessment Report
- Application_20240119005143
- Embodied Emissions Materials Form
- Environmental Impact Statement - Summit at Kemps Creek_
- RFI Appendix A - NABERS Reverse Calculators (Water)
- RFI Appendix A -NABERS Reverse Calculators (Energy)
- The Summit - Net Zero Statement
Response to Submissions4
Agency Advice24
- 7 July 2025 Response to CPHR
- Advice on 2nd RTS - CPHR
- Advice on Amendment Report - DCCEEW Aboriginal Cultural Heritage
- Advice on Amendment Report - DCCEEW Biodiversity
- Advice on Amendment Report - Fire and Rescue NSW
- Advice on Amendment Report - Penrith Council
- Advice on Amendment Report - Sydney Water
- Advice on Amendment Report - Sydney Water attach
- Advice on Amendment Report - TfNSW
- Advice on Amendment Report - TfNSW Freight
- Advice on Amendment Report - West Syd Airport
- Advice on EIS - Biodiversity, Science and Conservation Group DCCEEW
- Advice on EIS - Fire and Rescue NSW
- Advice on EIS - Heritage NSW
- Advice on EIS - Penrith City Council
- Advice on EIS - RFS
- Advice on EIS - Sydney Water
- Advice on EIS - TfNSW
- Advice on EIS - Water NSW
- Advice on Second RTS - Penrith Council
- CPHR RTS advice (July 2025)
- CPHR comment on RTS
- Final Water & Stormwater Management Plan
- TfNSW Concurrence 13 Feb 2026
Amendments49
- Amendment Acceptance Letter 7 Feb 2025
- Appendix A - Submissions Register
- Appendix AA - Updated Biodiversity CEMP
- Appendix B - Updated Consolidated Mitigation Measures
- Appendix BB - Fauna Management Plan
- Appendix C1 - Amended Architectural Drawings
- Appendix C2 - Amended Architectural Drawings
- Appendix CC - Dam Decommissioning Plan
- Appendix D1 - Amended Estate Civil Drawings
- Appendix D2 - Amended Estate Civil Drawings
- Appendix D3 - Amended Estate Civil Drawings
- Appendix D4 - Amended Estate Civil Drawings
- Appendix DD - Geotechincal Cover Letter
- Appendix E - Amended Landscape Drawings
- Appendix EE - Updated Detailed Site Investigation
- Appendix F - Amended Plan of Subdivision
- Appendix FF - Updated Remedial Action Plan
- Appendix G - Northern Access Works Drawings
- Appendix GG - Ancillary Remediation Area Assessment
- Appendix H - Updated Statutory Compliance Table
- Appendix HH - Updated BCA Assessment Report
- Appendix I - Mamre Road Precinct DCP Compliance Table
- Appendix II - Updated Waste Management Plan
- Appendix J - Updated Engagement Outcomes Report
- Appendix JJ - ESD Report Cover Letter
- Appendix K - Earthworks Report
- Appendix KK - CPTED Report Cover Letter
- Appendix L - Updated Civil Infrastructure Report
- Appendix LL - Aeronautical Impact Statement
- Appendix M - Updated Water and Stormwater Management Plan
- Appendix MM - TfNSW DFR Trunk Drainage Consultation
- Appendix N - Erosion and Sediment Control Plan
- Appendix NN - Schools Access Travel Time Assessment
- Appendix O - Addendum Flood Impact Assessment
- Appendix P - Addendum TMAP
- Appendix Q - Updated Noise Impact Assessment
- Appendix R - Updated Air Quality Impact Assessment
- Appendix S - Updated Visual Impact Assessment
- Appendix T - Updated Hazard and Risk Assessment
- Appendix U - Updated Bushfire Assessment Report
- Appendix V - Addendum Social and Economic Impact Assessment
- Appendix W - Updated ACHA (Redacted)
- Appendix X - Addendum Historical Heritage Impact Assessment
- Appendix Y - Updated BDAR
- Appendix Z - Weed Eradication Management Plan
- Land Owner's Consent - 1-51 Aldington (SSD-30628110)
- Land Owner's Consent - GPT Pty Limited (SSD-30628110)
- Land Owner's Consent - Penrith City Council (SSD-30628110)
- Submissions & Amendment Report - Summit at Kemps Creek
Additional Information13
- 24-02-16 - Minor RFI Letter
- Advice on Amendment Report - DPHI 24 March 2025
- Appendix A - Submissions Register
- Appendix B - Updated Elevation Drawings
- Appendix C - Updated Northern Access Works Drawings
- Appendix D - Updated Consolidated Mitigation Measures
- Appendix E - Draft Net Developable Area Plan
- Appendix F - Updated Plan of Subdivision
- Appendix G - Updated BDAR
- Appendix H - Updated Estate Civil Drawings
- Appendix I - Updated Water & Stormwater Management Plan
- Submissions Report - Summit at Kemps Creek (SSD-30628110)
- Updated Noise Impact Assessment May 2025
What's near it
Where it is
- Suburb
- Kemps Creek
- Council area
- Penrith
Source ABS suburbs and localities and local government areas (ASGS 2021), CC BY 4.0
Other State projects near it
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0; straight-line distance
Nearest schools
Source NSW Department of Education, CC BY; straight-line distance
Nearest hospitals
Source AIHW MyHospitals, CC BY 4.0; straight-line distance
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project
Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.