Decided: approved on 20 Feb 2026Industry and warehousesDistrict scale

Where it is in the process

Approved on 20 Feb 2026

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination20 Feb 2026 (done)
  9. Approved20 Feb 2026

What it proposes

AI summary. Written from this project's page and its SSD-30628110 Assessment Report and SSD-30628110 Development Consent on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

Summit at Kemps Creek warehouse estate, Mamre Road

The project is a warehouse estate at 706-752 Mamre Road, Kemps Creek, in the Penrith council area, on a site of 52 ha. It is a concept proposal for eight buildings with 244,809 m² of gross floor area, plus a Stage 1 application for three buildings with 79,888 m² of floor area, site-wide earthworks and roads. It includes part of the Southern Link Road. The department gives a capital investment of $489 million for the concept proposal and 1,716 operational jobs.

The application was exhibited from 19 Mar 2024 to 15 Apr 2024, and the amended application from 11 Feb 2025 to 10 Mar 2025. The portal counts 7 submissions, all comments. The department recommended approval, and its Executive Director, as the Minister's delegate, approved it on 20 Feb 2026 with conditions. Next, the proponent must meet those conditions, and the later buildings need their own applications.

Capital investment (concept proposal)
$489MSSD-30628110 Assessment Report
Concept proposal floor area
244,809 m²SSD-30628110 Assessment Report
Stage 1 floor area
79,888 m²SSD-30628110 Assessment Report
Operational jobs (concept proposal)
1,716 jobsSSD-30628110 Assessment Report
Construction jobs (concept proposal)
1,981 jobsSSD-30628110 Assessment Report
Stage 1 capital investment
$235MSSD-30628110 Assessment Report
Site area
52 haSSD-30628110 Assessment Report
Concept proposal buildings
8 buildingsSSD-30628110 Assessment Report

The department's description

A Concept Proposal comprising nine buildings with a total gross floor area (GFA) of up to 244,413 square metres (m2) and Stage 1 development of three buildings with a total GFA of 79,263 m2.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

7 submissions: 6 from organisations and 1 from public authorities

Object0
Support0
Comment7

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

151 documents in 9 folders, each on the NSW Planning Portal

Notice of Exhibition2
Request for SEARs2
SEARs4
EIS50
Response to Submissions4
Agency Advice24
Amendments49
Additional Information13
Determination3

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.