On the map
State significant development

1-51 Aldington Road Industrial Estate

Three warehouses at 1-51 Aldington Road, Kemps Creek

Under way: at prepare eisIndustry and warehousesNeighbourhood scale

Where it is in the process

At prepare eis

  1. SEARs (done)
  2. Prepare EIS (current stage)
  3. Exhibition (to come)
  4. Collate Submissions (to come)
  5. Response to Submissions (to come)
  6. Assessment (to come)
  7. Recommendation (to come)
  8. Determination (to come)

What it proposes

AI summary. Written from this project's page and its 1-51 Aldington Road Scoping Report_FINAL on the NSW Planning Portal, on 19 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

Three warehouses at 1-51 Aldington Road, Kemps Creek

The proponent proposes an industrial estate at 1-23 and 25-51 Aldington Road, Kemps Creek, in the Penrith area, on a site of about 202,800 m². It would build three single-storey warehouses with about 47,365 m² of warehouse floor area and 2,530 m² of ancillary office space, with 292 car parking spaces. The site would be subdivided into two development lots and an environmental conservation lot. The scoping report gives an estimated development cost of $133 million for the overall project.

The case is at the stage where the proponent prepares its environmental impact statement (EIS). A scoping report dated 12 Aug 2024 was submitted, and amended Secretary's environmental assessment requirements (SEARs) have been issued. Next, the EIS is to be exhibited and the public can make submissions. No submissions have been received so far. The department then assesses the project and it is determined.

Estimated development cost
$133M1-51 Aldington Road Scoping Report_FINAL
Warehouse floor area
47,365 m²1-51 Aldington Road Scoping Report_FINAL
Ancillary office space
2,530 m²1-51 Aldington Road Scoping Report_FINAL
Car parking spaces
292 car spaces1-51 Aldington Road Scoping Report_FINAL
Site area
202,800 m²1-51 Aldington Road Scoping Report_FINAL

The department's description

Construction of an industrial estate comprising bulk earthworks, construction of three warehouses and ancillary office space, car parking, estate roads, landscaping, stormwater infrastructure, services and subdivision.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.