On the map
State significant development

Narrandera Solar Farm

A 200 MW solar farm and 400 MW battery at Gillenbah

Under way: at searsEnergy: solarDistrict scale

Where it is in the process

At sears

  1. SEARs (current stage)
  2. Prepare EIS (to come)
  3. Exhibition (to come)
  4. Collate Submissions (to come)
  5. Response to Submissions (to come)
  6. Assessment (to come)
  7. Recommendation (to come)
  8. Determination (to come)

What it proposes

AI summary. Written from this project's page and its Narrandera Solar Farm Scoping Report on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

A 200 MW solar farm and 400 MW battery at Gillenbah

The proponent proposes a solar farm of about 200 MW with a battery energy storage system of 400 MW and up to 3,200 MWh, at 1004 The Gap Road, Gillenbah, in the Narrandera Shire. The land under investigation covers about 1,085 ha, roughly 15 km south of Narrandera. Sheep grazing would continue under the panels. The project would connect to an existing high voltage transmission line. No capital investment is stated.

The case is at the early stage of preparing the Secretary's environmental assessment requirements (SEARs), which set what the environmental impact statement (EIS) must cover. The scoping report is dated December 2025. No public submissions have been made. Next, the department issues the SEARs, the proponent prepares an EIS, and it is exhibited so the public can make submissions.

Solar farm capacity
200 MWNarrandera Solar Farm Scoping Report
Battery power capacity
400 MWNarrandera Solar Farm Scoping Report
Battery storage capacity
3,200 MWhNarrandera Solar Farm Scoping Report
Land under investigation
1,085 haNarrandera Solar Farm Scoping Report

The department's description

Construction, operation, and decommissioning of a Solar Farm with a capacity of approximately 200 MW, a battery energy storage system (BESS) with a capacity of approximately 400 MW / 3200 MWh, and ancillary infrastructure.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.