Approved on 8 Aug 2019

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination8 Aug 2019 (done)
  9. Approved8 Aug 2019

What it proposes

The department's description

Development of a 200 megawatt solar farm with battery storage and associated infrastructure.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Modifications

2 changes to the project after its decision, each assessed as a case of its own, newest first.

MOD 2 - Changes to Battery Storage SystemSSD-9031-Mod-2

Decided: approved on 31 May 2021 by the department (director)

Move from a centralised to decentralised and increase the capacity of the battery energy storage system.

Its 5 documents

5 documents in 3 folders, each on the NSW Planning Portal

Modification Application1

See the document on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

MOD 1 - Disturbance footprint and intersection changeSSD-9031-Mod-1

Decided: approved on 24 Nov 2020 by the department (director)

Update project layout, redesign internal road network and site access, remove the Basic Left Turn at Muntz and Sandingo Roads intersection.

Its 7 documents

7 documents in 5 folders, each on the NSW Planning Portal

Preparation of Modification Report1

See the document on the Planning Portal

Modification Application1

See the document on the Planning Portal

Additional Information2

See the 2 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

87 documents in 9 folders, each on the NSW Planning Portal

Request for SEARs1
SEARs1
EIS14
Response to Submissions9
Determination3
Management Plans and Strategies43
Independent Reviews and Audits3
Notifications4
Other Documents9

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.