Mangoplah Battery Energy Storage System

A 100 MW battery on Holbrook Road, Mangoplah

Decided: approved on 5 Nov 2026Energy: batteriesDistrict scale

Where it is in the process

Approved on 5 Nov 2026

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination5 Nov 2026 (done)
  9. Approved5 Nov 2026

What it proposes

AI summary. Written from this project's page and its Assessment Report and Instrument of Consent on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

A 100 MW battery on Holbrook Road, Mangoplah

The project is a battery energy storage system with a nominal capacity of 100 MW and 400 MWh, at 4178 Holbrook Road, Mangoplah, in the Wagga Wagga City Council area. It includes an on-site substation and overhead lines connecting to an existing 132 kV transmission line, and an upgraded access road off Holbrook Road. The development footprint is 4.31 ha. The department gives a development cost of $165 million, up to 60 construction jobs and 2 operational jobs.

The environmental impact statement (EIS) was exhibited from 20 Nov 2025 to 17 Dec 2025 and drew 189 submissions: 187 objecting, 1 supporting and 1 commenting. The proponent amended the project in June 2026. The department's Deputy Secretary approved it on 5 Nov 2026, as the Minister's delegate, with conditions. The consent caps the battery at 106 MW and 423 MWh. Next, the proponent must meet the conditions, including a voluntary planning agreement with the council, before construction.

Estimated development cost
$165MAssessment Report
Battery power capacity
100 MWAssessment Report
Battery storage capacity
400 MWhAssessment Report
Construction jobs
60 jobsAssessment Report
Operational jobs
2 jobsAssessment Report
Development footprint
4.31 haAssessment Report
Maximum discharge capacity allowed by consent
106 MWInstrument of Consent
Maximum storage capacity allowed by consent
423 MWhInstrument of Consent

The department's description

Construction, operation, and decommissioning of a battery energy storage system (BESS) with a capacity of 100MW/400MWh and ancillary infrastructure.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

189 submissions: 181 from the public, 7 from organisations and 1 from public authorities

Object187
Support1
Comment1

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

77 documents in 9 folders, each on the NSW Planning Portal

Notice of Exhibition1
Request for SEARs1
SEARs1
EIS18
Response to Submissions6
Agency Advice38
Amendments3
Additional Information6
Determination3

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.