On the map
State significant development

Livingstone Solar Farm

A 600 MW solar farm and battery at Gregadoo, near Wagga Wagga

Under way: at prepare eisEnergy: solarRegional scale

Where it is in the process

At prepare eis

  1. SEARs (done)
  2. Prepare EIS (current stage)
  3. Exhibition (to come)
  4. Collate Submissions (to come)
  5. Response to Submissions (to come)
  6. Assessment (to come)
  7. Recommendation (to come)
  8. Determination (to come)

What it proposes

AI summary. Written from this project's page and its Scoping Report on the NSW Planning Portal, on 19 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

A 600 MW solar farm and battery at Gregadoo, near Wagga Wagga

The proponent proposes a solar farm and battery energy storage system on a family farm at Gregadoo and Big Springs, in the Wagga Wagga City Council area. The portal describes a 600 MW solar farm. The scoping report gives a solar capacity of between 300 and 600 MW and a battery of 400 MW / 1,600 MWh. The site is about 2,700 ha, and development would cover up to about 1,345 ha. It would connect to the planned Gugaa Substation on the approved HumeLink transmission line. No capital investment or job numbers are stated.

The proponent is preparing an environmental impact statement (EIS). The scoping report is dated 11 Feb 2025, and the Secretary's environmental assessment requirements (SEARs) were issued on 10 Mar 2025. Next, the EIS is lodged and exhibited, when the public can make submissions. No submissions have been made yet. The department then assesses the project.

Solar farm capacity (portal description)
600 MWPortal page
Battery power capacity
400 MWScoping Report
Battery storage capacity
1,600 MWhScoping Report
Project site area
2,700 haScoping Report
Maximum development area
1,345 haScoping Report

The department's description

Development of a 600 MW solar farm with battery storage and associated infrastructure.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 19 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.