Whitehaven Solar Farm
A 20 MW solar farm and battery at Kurrajong Creek Road, Narrabri
Where it is in the process
Approved on 21 Sep 2026
What it proposes
AI summary. Written from this project's page and its Conditions of Consent and Whitehaven Solar - Assessment Report on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it
A 20 MW solar farm and battery at Kurrajong Creek Road, Narrabri
The project is a 20 MW solar farm with a battery storage system of up to 10 MW and 10 MWh, about 25 km south-east of Narrabri in the Narrabri Shire area. It would use about 50,000 solar panels and a new 66 kilovolt power line, and supply electricity to the adjacent Narrabri Mine. The estimated cost is $56.6 million, with up to 65 construction jobs and 1 operational job. The development footprint is about 88.49 ha.
The environmental impact statement (EIS) was exhibited from 13 Feb 2025 to 13 Mar 2025 and drew 62 submissions on the portal page: 59 objecting, 1 supporting and 2 commenting. The council did not object. The department's assessment report of September 2026 found the project approvable subject to conditions. The department's Executive Director, as the Minister's delegate, approved it on 21 Sep 2026. Next, the proponent must meet the conditions of consent, including plans for traffic and heritage, before work starts.
- Capital investment
- $56.6MWhitehaven Solar - Assessment Report
- Solar generating capacity
- 20 MWPortal page
- Battery power capacity
- 10 MWWhitehaven Solar - Assessment Report
- Battery storage capacity
- 10 MWhWhitehaven Solar - Assessment Report
- Construction jobs
- 65 jobsWhitehaven Solar - Assessment Report
- Operational jobs
- 1 jobsWhitehaven Solar - Assessment Report
- Development footprint
- 88.49 haWhitehaven Solar - Assessment Report
- Site area
- 100 haWhitehaven Solar - Assessment Report
The department's description
Whitehaven Solar Farm , adjacent to the existing Narrabri Mine which includes the construction, operation and decommissioning of a solar photovoltaic energy generating facility with a 20MW capacity.
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0
Submissions
What the public, organisations and public authorities said, counted by where they stood.
62 submissions: 51 from the public, 10 from organisations and 1 from public authorities
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal
Documents
By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.
81 documents in 9 folders, each on the NSW Planning Portal
Notice of Exhibition1
Request for SEARs1
SEARs1
EIS24
- EIS Appendix A - Biodiversity Development Assessment Report
- EIS Appendix B - Aboriginal Cultural Heritage Assessment
- EIS Appendix C - Agricultural Impact Assessment
- EIS Appendix D - Landscape and Visual Impact Assessment
- EIS Appendix E - Road Transport Assessment
- EIS Appendix F - Glint and Glare Assessment
- EIS Appendix G - Water Resources Assessment
- EIS Appendix H - Land Contamination Assessment
- EIS Appendix I - Social Impact Assessment
- EIS Appendix J - Noise Impact Assessment
- EIS Appendix K - Environmental Risk Assessment
- EIS Application Form
- EIS Application Form
- EIS Attachment 1 - SEARs
- EIS Attachment 2 - DA Area and Real Property
- EIS Attachment 3 - Land Ownership and Landholder Key
- EIS Attachment 4 - Strategic Planning Statements & Pol.
- EIS Attachment 5 - Relevant Planning Instruments & Leg.
- EIS Attachment 6 - Summary of Mitigation Measures
- EIS Attachment 7 - Estimated Development Cost
- EIS Attachment 8 - Summary of Community Consultation
- EIS Executive Summary
- EIS Submission Form
- Environmental Impact Statement
Response to Submissions2
Agency Advice38
- CPHR RTS Advice
- CPHR response - RFI
- Crown Lands EIS Advice
- Crown Lands SEARs Advice
- DCCEEW CPHR EIS Advice
- DCCEEW CPHR SEARs Advice
- DCCEEW Water EIS Advice
- DCCEEW Water RTS Advice
- DPIRD Agriculture EIS Advice
- DPIRD Agriculture SEARs Advice
- DPIRD Fisheries EIS Advice
- DPIRD Fisheries SEARs Advice
- DPIRD RTS Advice
- FRNSW - Whitehaven Solar Farm - RFI - SSD-66542218
- FRNSW EIS Advice
- FRNSW SEARs Advice
- HNSW ACH RTS Advice
- HNSW ACH RTS Advice
- Heritage Council of NSW EIS Advice
- Heritage NSW (ACH) EIS Advice
- Heritage NSW (ACH) SEARs Advice
- Heritage NSW SEARs Advice
- MEG SEARs Advice
- NSC Advice on EIS
- NSC RTS Advice
- NSW Resources EIS Advice
- NSW SES RTS Advice
- NSWR RTS Advice
- Narrabri Shire Council SEARs Advice
- RFS EIS Advice
- SA RTS Advice
- SES RTS Advice
- Subsidence Advisory Advice on EIS
- Subsidence Advisory SEARs Advice
- TFNSW Response to Whitehaven SF RFI
- TfNSW EIS Advice
- TfNSW RTS Advice
- TfNSW SEARs Advice
Additional Information9
Determination3
What's near it
Where it is
Source ABS suburbs and localities and local government areas (ASGS 2021), CC BY 4.0
Other State projects near it
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0; straight-line distance
Nearest schools
Source NSW Department of Education, CC BY; straight-line distance
Nearest hospitals
Source AIHW MyHospitals, CC BY 4.0; straight-line distance
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project
Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.