On the map
State significant development

Narrabri Underground Mine Stage 3 Extension Project

Decided: approved on 1 Apr 2022Mining

Where it is in the process

Approved on 1 Apr 2022

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination1 Apr 2022 (done)
  9. Approved1 Apr 2022

What it proposes

The department's description

Extension of the approved Narrabri Underground Coal Mine

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

82 submissions: 61 from the public, 6 from organisations and 15 from public authorities

Object3
Support63
Comment16

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

3 changes to the project after its decision, each assessed as a case of its own, newest first.

MOD 3 - Bord and Pillar Mining LW203-LW204SSD-10269-Mod-3

Under way: at prepare mod report

Undertake bord and pillar mining in parts of LW203 and LW204, extracting approximately 0.64 Mt ROM coal from approved mine areas not accessible by longwall mining

Its 1 documents

1 document in 1 folder, each on the NSW Planning Portal

Early Consultation1

See the document on the Planning Portal

Its page on the Planning Portal

MOD 2 - Bord and Pillar Mining ExtensionSSD-10269-Mod-2

Under way: at prepare mod report

Extension of the current bord and pillar mining operations at the Narrabri Mine to allow for extraction of additional coal reserves within the Hoskissons Coal Seam.

Its 2 documents

2 documents in 1 folder, each on the NSW Planning Portal

Early Consultation2

See the 2 documents on the Planning Portal

Its page on the Planning Portal

MOD 1 - Biodiversity ConditionsSSD-10269-Mod-1

Decided: approved on 18 Dec 2025 by the department (director)

The modification includes amending Condition B39, Schedule 2 to revise biodiversity offset phases, amending Condition B40, Schedule 2 to allow for the reduction of any species credit type in table 6 and the removal of an approved Stage 3 vent area.

Its 12 documents

12 documents in 6 folders, each on the NSW Planning Portal

Early Consultation1

See the document on the Planning Portal

Modification Application1

See the document on the Planning Portal

Agency Advice3

See the 3 documents on the Planning Portal

Additional Information5

See the 5 documents on the Planning Portal

Determination1

See the document on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.