On the map
State significant infrastructure

Narrabri Lateral Pipeline

A 55 km gas pipeline from Leewood to Baan Baa, Narrabri

Under way: at assessmentEnergy: otherRegional scale

Where it is in the process

At assessment

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (current stage)
  7. Recommendation (to come)
  8. Determination (to come)

What it proposes

AI summary. Written from this project's page and its Executive summary on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

A 55 km gas pipeline from Leewood to Baan Baa, Narrabri

The proponent proposes an underground gas transmission pipeline about 55 kilometres long, from the approved Narrabri Gas Project at Leewood, south-west of Narrabri, to the approved Hunter Gas Pipeline near Baan Baa, in the Narrabri Shire. The pipeline would be about 508 mm wide, carry up to 200 terajoules a day and sit in a 30 m wide easement. Construction would need a peak workforce of up to about 200 people. The environmental impact statement (EIS) estimates direct expenditure of $120 million and clearing of about 168.34 ha of native vegetation.

The EIS was exhibited and drew 375 submissions: 314 objecting, 56 supporting and 5 commenting. The proponent has responded to submissions and amended the application, and the department is assessing it. Next, the department prepares its assessment report, and the Minister for Planning decides. The proponent expects to start construction around the end of 2026 if approved.

Pipeline length
55 kmExecutive summary
Pipeline capacity
200 terajoules a dayExecutive summary
Easement width
30 mExecutive summary
Peak construction workforce
200 peopleExecutive summary
Direct expenditure
$120MExecutive summary
Native vegetation cleared
168.34 haExecutive summary
Public submissions
375 submissionsPortal page
Submissions objecting
314 submissionsPortal page

The department's description

Approximately 55 km long gas pipeline connecting the Narrabri Gas Project to the Queensland Hunter Gas Pipeline

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

375 submissions: 339 from the public, 35 from organisations and 1 from public authorities

Object314
Support56
Comment5

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

94 documents in 7 folders, each on the NSW Planning Portal

Notice of Exhibition2
Application1
SEARs14
EIS47
Response to Submissions2
Agency Advice16
Amendments12

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.