Decided: approved on 28 Nov 2022Water and sewerage

Where it is in the process

Approved on 28 Nov 2022

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination28 Nov 2022 (done)
  9. Approved28 Nov 2022

What it proposes

The department's description

Concept and Stage 1 development application for an Advanced Water Recycling Centre to provide wastewater services and recycled water for the Aerotropolis and South West Growth Areas and associated pipelines.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

20 submissions: 4 from the public, 2 from organisations and 14 from public authorities

Object3
Support3
Comment14

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

3 changes to the project after its decision, each assessed as a case of its own, newest first.

MOD 3 - Revised Operational Concentration LimitsSSI-8609189-Mod-3

Decided: approved on 20 Jun 2025 by the department (team leader)

The proposed modification seeks to vary the concentration limits for treated water releases to the Nepean River and provide separate concentration limits for advanced and tertiary treated water releases.

Its 15 documents

15 documents in 5 folders, each on the NSW Planning Portal

Modification Application2

See the 2 documents on the Planning Portal

Agency Advice6

See the 6 documents on the Planning Portal

Additional Information4

See the 4 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Consolidated Approval1

See the document on the Planning Portal

Its page on the Planning Portal

MOD 2 - Pipeline RealignmentsSSI-8609189-Mod-2

Decided: approved on 10 Oct 2023 by the department (executive director) · 5 submissions

The proposed modification includes realignments of the treated water and brine pipelines, and relocation of the flow splitter structure / valve station.

Its 27 documents

27 documents in 7 folders, each on the NSW Planning Portal

Notice of Exhibition1

See the document on the Planning Portal

Modification Application9

See the 9 documents on the Planning Portal

Response to Submissions2

See the 2 documents on the Planning Portal

Agency Advice7

See the 7 documents on the Planning Portal

Additional Information4

See the 4 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Approval1

See the document on the Planning Portal

Its page on the Planning Portal

MOD 1 - Removal of Environmental Flows PipelineSSI-8609189-Mod-1

Decided: approved on 26 May 2023 by the department (team leader) · 5 submissions

The Proponent proposes to remove the 4.5km environmental flows pipeline from the project approval. This includes removing the trenched and tunnelled sections of pipeline and release structure at Warragamba River.

Its 17 documents

17 documents in 6 folders, each on the NSW Planning Portal

Notice of Exhibition1

See the document on the Planning Portal

Modification Application5

See the 5 documents on the Planning Portal

Response to Submissions2

See the 2 documents on the Planning Portal

Agency Advice5

See the 5 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Approval1

See the document on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.