Tamworth Battery Energy Storage System
A 200 MW battery on Burgmanns Lane, Kingswood
Where it is in the process
At response to submissions
What it proposes
AI summary. Written from this project's page and its Tamworth BESS EIS on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it
A 200 MW battery on Burgmanns Lane, Kingswood
The proponent proposes a battery energy storage system with a capacity of 200 MW, with associated infrastructure, at 696 Burgmanns Lane, Kingswood, in the Tamworth Regional Council area. The description lists an on-site substation, an operations and maintenance building, parking and internal roads. No capital investment, storage capacity in MWh or job numbers are stated in the text available.
The case is at the response to submissions stage. The environmental impact statement (EIS) is dated 22 May 2024 and drew 132 submissions: 131 objecting and 1 commenting. A request for the proponent to respond to the submissions was issued in June 2024. Next, the proponent responds to the issues raised and may amend the project. The department then assesses it, with advice from other agencies, and a decision follows.
- Battery capacity
- 200 MWPortal page
- Public submissions
- 132 submissionsPortal page
- Submissions objecting
- 131 submissionsPortal page
The department's description
Development of a 200 MW battery energy storage facility with associated infrastructure
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0
Submissions
What the public, organisations and public authorities said, counted by where they stood.
132 submissions: 130 from the public and 2 from organisations
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal
Documents
By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.
35 documents in 5 folders, each on the NSW Planning Portal
Notice of Exhibition1
EIS12
- Appendix D Aboriginal Cultural Heritage Assessment
- Appendix E Biodiversity Assessment Report
- Appendix F Land Use Conflict Risk Assessment
- Appendix G Flood Impact Assessment
- Appendix H Traffic Impact Assessment
- Appendix J Visual Impact Assessment
- Appendix K Preliminary Hazard Assessment
- Appendix L Preliminary AES
- Application Form
- Tamworth BESS EDC
- Tamworth BESS EIS
- Tamworth BESS EIS Summary Report
Response to Submissions1
Agency Advice19
- Advice on EIS - Crown Lands
- Advice on EIS - DPI Fisheries
- Advice on EIS - Fire and Rescue
- Advice on EIS - Heritage NSW (ACH)
- Advice on EIS - Mining, Exploration and Geoscience
- Advice on EIS - NSW DCCEEW Water
- Advice on EIS - Tamworth Regional Council
- Advice on EIS - TfNSW
- Advice on EIS - Transgrid
- Advice on SEARs - BCS
- Advice on SEARs - DPIE Water
- Advice on SEARs - FRNSW
- Advice on SEARs - Heritage Council of NSW
- Advice on SEARs - NSW EPA
- Advice on SEARs - RFS
- Advice on SEARs - Tamworth Council
- Advice on SEARs - TfNSW
- Advice on SEARs - TransGrid
- Advice on SEARs – Mining, Exploration and Geoscience
What's near it
Where it is
- Suburb
- Kingswood
- Council area
- Tamworth Regional
Source ABS suburbs and localities and local government areas (ASGS 2021), CC BY 4.0
Other State projects near it
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0; straight-line distance
Nearest schools
Source NSW Department of Education, CC BY; straight-line distance
Nearest hospitals
Source AIHW MyHospitals, CC BY 4.0; straight-line distance
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project
Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.