State significant development

Calala Battery Energy Storage System

Decided: approved on 28 Jun 2024Energy: batteriesDistrict scale

Where it is in the process

Approved on 28 Jun 2024

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination28 Jun 2024 (done)
  9. Approved28 Jun 2024

What it proposes

The department's description

Development of a 300 MW / 600 MWh battery storage system and associated infrastructure including grid connection.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

27 submissions: 24 from the public and 3 from organisations

Object26
Support0
Comment1

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

1 change to the project after its decision, each assessed as a case of its own, newest first.

Modification 1 Calala BESS - s4.55(1A) Minor Modification WorksSSD-52786213-Mod-1

Decided: approved on 12 Jun 2026 by the department (director)

Proposed works to include new vehicle turning bays, road and vehicle access off Burgmanns Lane, minor works at the Tamworth Substation and BESS facility, and minor correction of boundaries.

Its 18 documents

18 documents in 5 folders, each on the NSW Planning Portal

Modification Application8

See the 8 documents on the Planning Portal

Agency Advice5

See the 5 documents on the Planning Portal

Additional Information2

See the 2 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.