AI summary. Written from this project's page and its SSD-78774218 - Environmental Impact Statement on the NSW Planning Portal, on 19 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it
Sydney Science Park concept and Stage 1 works, Luddenham
The proposal is a concept plan for Sydney Science Park at 565-601 and 601a Luddenham Road, Luddenham, in the Penrith council area. It covers super lots, open space, riparian corridors and key road links. Stage 1 would carry out initial enabling works, earthworks, key roads, infrastructure, landscaping, public domain and open space, and subdivide the land into 18 lots. No capital investment is stated.
The proponent's environmental impact statement (EIS), dated 24 Nov 2025, was exhibited and drew 3 submissions: 1 objecting, 1 supporting and 1 commenting. The proponent has responded to submissions and lodged an amendment report. The case is now at the "More Information Required" stage, so the department has asked for further information. Next, the department assesses the project, with advice from other agencies, before a report and a decision. No decision date is given.
- Lots in Stage 1 subdivision
- 18 lotsPortal page
- Public submissions
- 3 submissionsPortal page
The department's description
Concept proposal for the development of super lots, open space, riparian corridors and key road links.
Stage 1 initial enabling works, earthworks, key roads, infrastructure, landscaping, public domain, open space and subdivision of 18 lots.
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0
Submissions
What the public, organisations and public authorities said, counted by where they stood.
3 submissions: 2 from the public and 1 from public authorities
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal
Documents
By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.
148 documents in 8 folders, each on the NSW Planning Portal
Notice of Exhibition1
Request for SEARs11
- App I - Preliminary Infrastructure Services Stmt
- Appendix A - Concept and Stage 1 Plans
- Appendix B - Staging Plans
- Appendix D - Preliminary Civil Design Statement
- Appendix E - Preliminary IWCM Statement
- Appendix F - Preliminary Flood Statement
- Appendix G - Preliminary Ecological Statement
- Appendix H - Preliminary Transport Statement
- Appendix J - Preliminary Heritage Statement
- Request for SEARs_20241219030332
- SSP SSDA#1 - Scoping Report
SEARs1
EIS47
- Appendix A - SEARs Compliance Table
- Appendix AA - Utilities Infrastructure Assessment
- Appendix B - Statutory Compliance Table
- Appendix BB - Validation Advice
- Appendix C - Aerotropolis Precinct Plan Compliance Table
- Appendix CC - Aeronautical Impact Assessment
- Appendix D - Engagement Outcomes Report
- Appendix DD - Air Quality Impact Assessment
- Appendix E - Consolidated Mitigation Measures
- Appendix EE - Arboricultural Impact Assessment
- Appendix F - Consolidated Concept Design Guidelines
- Appendix FF - Bushfire Protection Assessment
- Appendix G - Aboriginal Heritage Assessment
- Appendix GG - Civil Strategy
- Appendix H - Biodiversity Development Assessment Report
- Appendix HH - Civil Engineering Plans
- Appendix I - Civil Design & Earthworks Strategy
- Appendix II - Construction Environmental Management Plan
- Appendix J - Concept Urban Structure Plan
- Appendix JJ - CNVMP
- Appendix K - Detailed Site Investigation
- Appendix KK - Construction Waste Management Plan
- Appendix LL - Dam Dewatering and Aquatic Fauna Management
- Appendix M - Flood Impact Assessment Report
- Appendix MM - Detailed Subdivision Plans
- Appendix N - Integrated Water Cycle Management Strategy
- Appendix NN - Ecologically Sustainable Development Report
- Appendix O - Open Space Strategy
- Appendix P - Riparian Assessment
- Appendix PP - Groundwater Impact Assessment
- Appendix Q - Urban Design Report and Staging Plan (Concept)
- Appendix QQ - Hazardous Building Materials Survey Report
- Appendix R - Vegetation Management Plan
- Appendix RR - Landscape Plans (Stage 1)
- Appendix S - Weed Eradication Management Plan
- Appendix SS - Landscape Report (Stage 1)
- Appendix T - Wildlife Hazard Assessment
- Appendix TT - Statement of Lighting Requirements
- Appendix U - Wildlife Hazard Management Plan
- Appendix UU - Transport Impact Assessment
- Appendix V - Connecting with Country Design Report
- Appendix VV - Urban Design Report (Detailed Stage 1)
- Appendix W - G & S Assessment
- Appendix X - Social Impact Assessment
- Appendix Y - State Design Review Response Report Response
- Appendix Z - Survey Plan
- SSD-78774218 - Environmental Impact Statement
Response to Submissions39
- Appendix D1 - Subdivision Plan
- Appendix D10 - Groundwater Impact Assessment
- Appendix D11 - Vegetation Management Plan
- Appendix D12 - Wildlife Hazard Assessment
- Appendix D13 - Wildlife Hazard Management Plan
- Appendix D14 - Dam Dewatering Aquatic Fauna Management
- Appendix D15 - Biodiversity Development Assessment Report
- Appendix D16 - Civil Engineering Response Letter
- Appendix D17 - Integrated Water Cycle Management Strategy
- Appendix D18 - Civil Design and Earthworks (Concept)
- Appendix D2 - Urban Design Response Letter
- Appendix D20 - open space on secondary high points
- Appendix D21 - Construction Access Strategy
- Appendix D22 - Traffic Response Letter
- Appendix D23 - Transport Impact Assessment
- Appendix D24 - Flood Response Letter
- Appendix D25 - Open Space Response Letter
- Appendix D26 - Landscape Plans (Stage 1)
- Appendix D27 - Open Space Strategy
- Appendix D28 - Landscape Strategy (Stage 1)
- Appendix D29 - Consolidated Concept Design Guideline
- Appendix D3 - Indicative Detailed Stage 1 Plans
- Appendix D30 - ESD Report (Concept)
- Appendix D31 - ESD Report (Stage 1)
- Appendix D32 - Water NSW Correspondence
- Appendix D33 - Heritage NSW Correspondence
- Appendix D36 - Engineering and Stormwater Strategy
- Appendix D37 - SSP Response to DCCEEW Water Group
- Appendix D38 - Temporary Potable Water Connection Package
- Appendix D39 - Summary Letter (Potable Water)
- Appendix D4 - Concept Urban Structure Plan
- Appendix D40 - Road Deviations
- Appendix D5 -Water Cycle Management Strategy Consultation
- Appendix D6 - Urban Design Report (Concept)
- Appendix D7 - Urban Design Report (Detailed Stage 1)
- Appendix D8 - Ecological Response Letter
- Appendix D9 - Biodiversity Management Plan
- Request RTS Letter
- SSD78774218 - Response to Submissions Report
Agency Advice37
- BDA advice on EIS
- CASA advice on EIS
- CPHR advice on EIS
- DCCEEW Water advice on EIS
- EPA advice on EIS
- FRNSW advice on EIS
- HNSW ACH advice on EIS
- HNSW advice on EIS
- Penrith Council advice on 8774218 - Council Advice on EIS
- RFS advice on EIS
- RTS: Council
- RTS: DCA (Heritage)
- RTS: Sydney Metro
- RTS: Sydney Metro 1
- RTS: TfNSW
- RTS: WSI
- SEARs - Bradfield Development Authority
- SEARs - CASA
- SEARs - CPHR
- SEARs - DCCEEW Water
- SEARs - EPA
- SEARs - Fire & Rescue NSW
- SEARs - Heritage NSW ACH
- SEARs - Heritage NSW EH
- SEARs - Penrith Council
- SEARs - RFS
- SEARs - Sydney Metro
- SEARs - Sydney Metro
- SEARs - Sydney Water
- SEARs - TfNSW
- SEARs - Water NSW
- SEARs - Western Sydney Airport
- Sydney Metro advice on EIS
- Sydney Metro advice on EIS 2
- TfNSW advice on EIS
- WNSW advice on EIS
- WSI advice on EIS
Amendments11
- Amended Application_20261027100327
- Amendment Acceptance Letter
- Appendix D1 - Stage 1 Civil Design Package
- Appendix D2 - Stage 1 Civil Engineering Strategy
- Appendix D3 - Transport Impact Assessment
- Appendix D4 - Stage 1 Landscape Report
- Appendix D5 - Stage 1 Landscape Documentation Package
- Appendix D6 - Urban Design Report (Detailed Stage 1)
- Appendix D7 - Concept Urban Structure Plan
- Appendix D8 - Subdivision Plans
- SSD-78774218 - Amendment Report
Additional Information1
What's near it
Where it is
Source ABS suburbs and localities and local government areas (ASGS 2021), CC BY 4.0
Other State projects near it
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0; straight-line distance
Nearest schools
Source NSW Department of Education, CC BY; straight-line distance
Nearest hospitals
Source AIHW MyHospitals, CC BY 4.0; straight-line distance
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project
Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.