New England Solar Farm

A 720 MW solar farm and battery near Uralla

Decided: approved on 9 Mar 2020OtherRegional scale

Where it is in the process

Approved on 9 Mar 2020

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination9 Mar 2020 (done)
  9. Approved9 Mar 2020

What it proposes

AI summary. Written from this project's page and its Development Consent and Assessment Report on the NSW Planning Portal, on 19 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

A 720 MW solar farm and battery near Uralla

The project is a solar farm with a generating capacity of about 720 MW and a 200 MW/400 MWh battery, east of Uralla and south of Armidale in the Uralla Shire. The development footprint is 2,061 ha of grazing land. It would create up to 700 construction jobs and 15 operational jobs. The capital investment is $768 million.

The environmental impact statement (EIS) drew 117 submissions: 66 objecting, 22 supporting and 29 commenting. The proponent amended the project, removing the southern array area and a construction accommodation village. The department's assessment report of December 2019 recommended approval. The Independent Planning Commission approved it on 9 Mar 2020, with conditions. Next, the proponent must meet those conditions, including preparing management plans, before construction starts.

Capital investment
$768MAssessment Report
Solar generating capacity
720 MWAssessment Report
Battery power capacity
200 MWAssessment Report
Battery storage capacity
400 MWhAssessment Report
Construction jobs
700 jobsAssessment Report
Operational jobs
15 jobsAssessment Report
Development footprint
2,061 haAssessment Report

The department's description

Development of a 720 MW solar farm with energy storage and associated infrastructure.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

117 submissions: 102 from the public and 15 from organisations

Object66
Support22
Comment29

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

2 changes to the project after its decision, each assessed as a case of its own, newest first.

New England Solar MOD 2SSD-9255-Mod-2

Decided: approved on 26 May 2023 by the department (director) · 3 submissions

Adding 127 ha of land to the project to accommodate a change to the project infrastructure layout and increasing the Battery Energy Storage System capacity.

Its 18 documents

18 documents in 7 folders, each on the NSW Planning Portal

Notice of Exhibition1

See the document on the Planning Portal

Modification Application1

See the document on the Planning Portal

Response to Submissions3

See the 3 documents on the Planning Portal

Agency Advice7

See the 7 documents on the Planning Portal

Additional Information2

See the 2 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

New England Solar MOD 1- Revised road upgrade disturbance boundariesSSD-9255-Mod-1

Decided: approved on 19 Feb 2021 by the department (director)

Minor increase in land clearance / disturbance area to enable vehicle access route and road upgrades.

Its 5 documents

5 documents in 3 folders, each on the NSW Planning Portal

Modification Application1

See the document on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

117 documents in 13 folders, each on the NSW Planning Portal

Request for SEARs2
SEARs2
EIS17
Response to Submissions1
Amendments1
Additional Information3
Recommendation2
Determination3
Management Plans and Strategies49
Reports1
Independent Reviews and Audits3
Notifications12
Other Documents21

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 19 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.