On the map
State significant development

Deeargee Solar

A 320 MW solar farm and battery at Gostwyck Road, Uralla

Under way: at prepare eisEnergy: solarRegional scale

Where it is in the process

At prepare eis

  1. SEARs (done)
  2. Prepare EIS (current stage)
  3. Exhibition (to come)
  4. Collate Submissions (to come)
  5. Response to Submissions (to come)
  6. Assessment (to come)
  7. Recommendation (to come)
  8. Determination (to come)

What it proposes

AI summary. Written from this project's page and its Deeargee Solar Addendum Scoping Report on the NSW Planning Portal, on 19 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

A 320 MW solar farm and battery at Gostwyck Road, Uralla

The proposal is a 320 MW solar farm with a battery energy storage system (BESS) and related infrastructure, about 12 km south-east of Uralla in the Uralla Shire. The battery would have a capacity of either 1400MW/2800MWh or 700MW/2800MWh. A February 2025 addendum adds a grid connection option: an easement about 14 km long to the Uralla 330 kV substation, with overhead towers up to about 65 m high. No capital investment or job numbers are stated.

The case is at the stage where the proponent prepares its environmental impact statement (EIS). The Secretary's environmental assessment requirements (SEARs) have been issued, and supplementary SEARs also exist. No submissions have been made yet. Next, the EIS is exhibited and the public can make submissions. The proponent then responds, and the department assesses the project and recommends a decision.

Solar farm capacity
320 MWPortal page
Battery option 1: power
1,400 MWPortal page
Battery storage capacity
2,800 MWhPortal page
Battery option 2: power
700 MWPortal page
Transmission line easement length
14 kmDeeargee Solar Addendum Scoping Report
Maximum tower height
65 mDeeargee Solar Addendum Scoping Report
Transmission easement impact area
45 haDeeargee Solar Addendum Scoping Report

The department's description

Construction, operation, and decommissioning of a 320MW Solar Farm, ancillary infrastructure, and a battery energy storage system (BESS) with a capacity of either 1400MW/2800MWh OR 700MW/2800MWh.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 19 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.