On the map
State significant development

New Eileen O'Connor School

A new special education school at 84 Gavenlock Road, Mardi

Under way: at response to submissionsEducationNeighbourhood scale

Where it is in the process

At response to submissions

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (current stage)
  6. Assessment (to come)
  7. Recommendation (to come)
  8. Determination (to come)

What it proposes

AI summary. Written from this project's page and its Environmental Impact Statement - Eileen O'Connor CS on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

A new special education school at 84 Gavenlock Road, Mardi

The proponent, Catholic Schools Broken Bay, proposes to subdivide land and build the Eileen O'Connor Catholic School for 200 students from Kindergarten to Year 12 with special needs. It would sit in the north-western corner of the St Peter's Catholic College site at 84 Gavenlock Road, Mardi, in the Central Coast Council area. The building would be part two and part three storeys, with 60 staff car parking spaces and 5 drop-off spaces. Keefers Glen would be widened to a 6 metre road corridor. The estimated development cost is stated as more than $20 million.

The environmental impact statement (EIS) was lodged in July 2025 and drew 118 submissions: 85 objecting, 11 supporting and 22 commenting. The case is at the response to submissions stage, where the proponent answers the issues raised and may amend the project. The department then assesses it, with advice from other agencies, and a decision follows.

Students
200 studentsEnvironmental Impact Statement - Eileen O'Connor CS
Estimated development cost (more than)
$20MEnvironmental Impact Statement - Eileen O'Connor CS
Staff car parking spaces
60 car spacesEnvironmental Impact Statement - Eileen O'Connor CS
Drop-off spaces
5 car spacesEnvironmental Impact Statement - Eileen O'Connor CS
Public submissions
118 submissionsPortal page

The department's description

Stage 1 development for a new Special Education school to cater for 200 students from Kindergarten to Year 12.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

118 submissions: 113 from the public, 4 from organisations and 1 from public authorities

Object85
Support11
Comment22

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

74 documents in 5 folders, each on the NSW Planning Portal

Notice of Exhibition1
SEARs3
EIS58
Response to Submissions2
Agency Advice10

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.