Wyong Battery Energy Storage System
A 200 MW battery at 320 Pacific Highway, Wyong
Where it is in the process
At prepare eis
What it proposes
AI summary. Written from this project's page and its Scoping Report on the NSW Planning Portal, on 19 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it
A 200 MW battery at 320 Pacific Highway, Wyong
The proponent proposes a battery energy storage system with a capacity of up to 200 MW over two hours, or up to 400 MWh, at 320 Pacific Highway, Wyong, in the Central Coast Council area. It would store electricity from the grid and release it at times of high demand. The batteries would connect to the existing Wyong Zone Substation by an underground cable. The site is about 5.5 ha, and the building and operating footprint would cover about 3.8 ha. No capital investment or job numbers are stated.
The case is at the stage where the proponent prepares an environmental impact statement (EIS). The Secretary's environmental assessment requirements (SEARs) have been issued, and the scoping report is dated 20 Nov 2025. Next, the EIS is exhibited and the public can make submissions. No submissions have been made yet. The department then assesses the project and decides it.
- Battery power capacity
- 200 MWScoping Report
- Battery storage capacity
- 400 MWhScoping Report
- Site area
- 5.5 haScoping Report
- Project area
- 3.8 haScoping Report
The department's description
Construction, operation, and decommissioning of a battery energy storage system (BESS) with a capacity of 200 MW/400 MWh and ancillary infrastructure.
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0
Documents
By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.
12 documents in 3 folders, each on the NSW Planning Portal
Request for SEARs1
What's near it
Where it is
- Suburb
- Wyong
- Council area
- Central Coast
Source ABS suburbs and localities and local government areas (ASGS 2021), CC BY 4.0
Other State projects near it
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0; straight-line distance
Nearest schools
Source NSW Department of Education, CC BY; straight-line distance
Nearest hospitals
Source AIHW MyHospitals, CC BY 4.0; straight-line distance
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 19 Nov 2026. See it on the map · Every State project
Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.