Lucca Road Data Centre Wyong
A 96 MW data centre at Lucca Road, Wyong
Where it is in the process
At prepare eis
What it proposes
AI summary. Written from this project's page and its Wyong Data Centre_SEARS_Scoping Report on the NSW Planning Portal, on 19 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it
A 96 MW data centre at Lucca Road, Wyong
The proponent proposes a data centre at 30 Lucca Road and 1 Pavitt Crescent, Wyong, in the Central Coast Council area, on a site of about 12.43 ha. The portal describes a load capacity of 96 MW in one two-storey building with offices, parking and landscaping. The scoping report adds 12 data halls, 85 car parking spaces and 108 back-up generators, with a total power consumption of about 150 MW. No capital investment or job numbers are stated.
The case is at the stage where the proponent prepares an environmental impact statement (EIS). The Secretary's environmental assessment requirements (SEARs) have been issued, and the scoping report is dated 24 Sep 2026. Next, the EIS is to be exhibited and the public can make submissions. There are no submissions yet. The proponent then responds, and the department assesses the project.
- Data centre load capacity
- 96 MWPortal page
- Total power consumption
- 150 MWWyong Data Centre_SEARS_Scoping Report
- Site area
- 12.43 haWyong Data Centre_SEARS_Scoping Report
- Car parking spaces
- 85 car spacesWyong Data Centre_SEARS_Scoping Report
- Back-up generators
- 108 generatorsWyong Data Centre_SEARS_Scoping Report
The department's description
Operation of a data centre with a load capacity of 96 MW comprising of one two-storey building, ancillary office space, car parking, landscaping and site works.
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0
Documents
By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.
13 documents in 3 folders, each on the NSW Planning Portal
Early Consultation9
- Appendix 1_Architectural Plans
- Appendix 2_Facade Study
- Appendix 3_Visual Impact Assessment
- Appendix 4_MEP Preliminary Design Basis Memo
- Appendix 5_Flood and Stormwater Technical Note
- Appendix 6_Aboriginal Assessment Statement
- Appendix 7_NSW Data Centre Guidelines Compliance Table
- Appendix 8_Approved Plans DA 647-2009
- Appendix 9_Development Consent DA 647-2009
Request for SEARs1
What's near it
Where it is
- Suburb
- Wyong
- Council area
- Central Coast
Source ABS suburbs and localities and local government areas (ASGS 2021), CC BY 4.0
Other State projects near it
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0; straight-line distance
Nearest schools
Source NSW Department of Education, CC BY; straight-line distance
Nearest hospitals
Source AIHW MyHospitals, CC BY 4.0; straight-line distance
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 19 Nov 2026. See it on the map · Every State project
Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.