On the map
State significant development

Jindera Solar Farm

Decided: approved on 22 Dec 2020Energy: solarDistrict scale

Where it is in the process

Approved on 22 Dec 2020

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination22 Dec 2020 (done)
  9. Approved22 Dec 2020

What it proposes

The department's description

Development of a 120 MW solar farm with energy storage and associated infrastructure.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

124 submissions: 111 from the public, 2 from organisations and 11 from public authorities

Object99
Support11
Comment14

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

2 changes to the project after its decision, each assessed as a case of its own, newest first.

Jindera Solar Mod 2 - Increase in BESS capacitySSD-9549-Mod-2

Under way: at prepare mod report

Increase in BESS capacity and removal of BESS staging.

Its page on the Planning Portal

Modification 1 - Underground Transmission LineSSD-9549-Mod-1

Decided: approved on 25 Oct 2023 by the department (director) · 11 submissions

Changes to project, including substitution of approved overhead transmission line with new underground transmission line.

Its 14 documents

14 documents in 6 folders, each on the NSW Planning Portal

Modification Application1

See the document on the Planning Portal

Response to Submissions1

See the document on the Planning Portal

Agency Advice6

See the 6 documents on the Planning Portal

Additional Information2

See the 2 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.