On the map
State significant development

Glenellen Solar Farm

Decided: approved on 15 Dec 2023Other

Where it is in the process

Approved on 15 Dec 2023

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination15 Dec 2023 (done)
  9. Approved15 Dec 2023

What it proposes

The department's description

Development of a 200 MW solar farm and associated infrastructure.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

122 submissions: 108 from the public and 14 from public authorities

Object81
Support27
Comment14

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

2 changes to the project after its decision, each assessed as a case of its own, newest first.

MOD 2-Transgrid accessSSD-9550-Mod-2

Decided: approved on 30 Apr 2025 by the department (director)

Change to the development area to include an access road from the TransGrid Jindera Zone Substation to the Glenellen Solar Farm Collector Substation.

Its 9 documents

9 documents in 5 folders, each on the NSW Planning Portal

Modification Application1

See the document on the Planning Portal

Agency Advice2

See the 2 documents on the Planning Portal

Additional Information3

See the 3 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Glenellen Solar Modification 1 Minor section 4.55(1) amendmentsSSD-9550-Mod-1

Decided: approved on 23 Aug 2024 by the department (director)

Modification to correct minor errors in consent

Its 4 documents

4 documents in 3 folders, each on the NSW Planning Portal

Modification Application1

See the document on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.