Griffith Base Hospital Redevelopment

Decided: approved on 14 Oct 2021Health

Where it is in the process

Approved on 14 Oct 2021

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination14 Oct 2021 (done)
  9. Approved14 Oct 2021

What it proposes

The department's description

The proposal includes the construction of a new four-storey hospital building, demolition of remaining buildings vacated after commissioning of the new hospital, site works including roads and on-grade car parking, landscaping and signage.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

7 submissions: 7 from public authorities

Object0
Support1
Comment6

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

5 changes to the project after its decision, each assessed as a case of its own, newest first.

Mod 3 - Green Travel Plan ModificationsSSD-9838218-Mod-3

Withdrawn: withdrawn

Modification of Conditions D19, E9 and E12 of the consent which require a detailed Green Travel Plan (GTP) and its annual update, and landscaping maintenance as per the Landscape Management Plan.

Its page on the Planning Portal

Modification 5 Minor change to Building 35 entrySSD-9838218-Mod-5

Decided: approved on 20 May 2026 by the department (team leader)

Minor refinements to the entrance of Building 35 including retention of a blade wall, a door change and revised form for the awning.

Its 7 documents

7 documents in 3 folders, each on the NSW Planning Portal

Modification Application3

See the 3 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Griffith Hospital Redev MOD 4 - GTP & landscapingSSD-9838218-Mod-4

Decided: approved on 2 Jul 2025 by the department (team leader)

Modification of conditions D19, E9 and E12 regarding the green travel plan requirements and its annual update, and landscaping maintenance as per the Landscape Management Plan.

Its 5 documents

5 documents in 3 folders, each on the NSW Planning Portal

Modification Application2

See the 2 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Griffith Hospital Redev MOD 2 - Bld 35 retentionSSD-9838218-Mod-2

Decided: approved on 10 Apr 2024 by the department (team leader)

Retention of Building No.35 (Paediatric Building) and changes to its entry, requiring a minor reconfiguration of the parking layout and landscaping.

Its 15 documents

15 documents in 3 folders, each on the NSW Planning Portal

Modification Application11

See the 11 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Griffith Hospital Redev MOD 1 - Design changesSSD-9838218-Mod-1

Decided: approved on 28 Sep 2023 by the department (team leader)

This modification application seeks consent for modifications including to plant services, façade articulation and detail, the removal of a Eucalyptus tree (tree 170) and the construction of a concrete hardstand for use by fire brigade trucks.

Its 12 documents

12 documents in 4 folders, each on the NSW Planning Portal

Modification Application7

See the 7 documents on the Planning Portal

Additional Information2

See the 2 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.