What it proposes

AI summary. Written from this project's page and its Scoping Report on the NSW Planning Portal, on 19 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

Decommissioning the Eraring Power Station site, Eraring

The proponent proposes to decommission the Eraring Power Station site at Rocky Point Road, Eraring, in the Lake Macquarie City Council area. The project would demolish the built infrastructure, including the cooling water system, and rehabilitate the landform. It would also continue recovering ash from the Eraring Ash Dam and build a hazardous materials disposal facility and borrow pits. The site covers about 1,100 ha, and the power station has a total capacity of 2,922 MW. No capital investment or job numbers are stated. Future uses of the site are not part of the project.

The proponent's scoping report is dated 10 Sep 2026, and the Secretary's environmental assessment requirements (SEARs) have been issued. The proponent is now preparing an environmental impact statement (EIS). Next, the EIS would be exhibited for public submissions, then assessed by the department. No submissions have been made yet. The Minister for Planning and Public Spaces is named as the approval authority.

Eraring Site area
1,100 haScoping Report
Power station total capacity
2,922 MWScoping Report
Ash dam storage area
250 haScoping Report

The department's description

The project involves the decommissioning of built infrastructure at Eraring Power Station, rehabilitation of the landform, ongoing resource recovery from the Eraring ash dam and other ancillary development.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

3 documents in 2 folders, each on the NSW Planning Portal

Request for SEARs1
SEARs2

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 19 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.