On the map
State significant development

Eraring Power Station - Ash Dam Expansion

Decided: approved on 29 Apr 2008Energy: other

Where it is in the process

Approved on 29 Apr 2008

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Assessment (done)
  6. Recommendation (done)
  7. Determination29 Apr 2008 (done)
  8. Approved29 Apr 2008

What it proposes

The department's description

Expansion of ash dam and changes to the ash disposal method and ancillary infrastructure.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Modifications

2 changes to the project after its decision, each assessed as a case of its own, newest first.

MOD 2 Ash Recycling FacilitiesMP07_0084-Mod-2

Decided: approved on 21 Jun 2022 by the department (executive director) · 47 submissions

Construction of additional ash storage silos and increase to ash recycling capacity

Its 23 documents

23 documents in 7 folders, each on the NSW Planning Portal

Notice of Exhibition1

See the document on the Planning Portal

Modification Application1

See the document on the Planning Portal

Response to Submissions2

See the 2 documents on the Planning Portal

Agency Advice8

See the 8 documents on the Planning Portal

Additional Information7

See the 7 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Eraring Power Station MOD 1 - Ash Dam ExpansionMP07_0084-Mod-1

Decided: approved on 23 Dec 2019 by the Independent Planning Commission · 30 submissions

Increasing the storage capacity of the Eraring Power Station Ash Dam.

Its 24 documents

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.