AI summary. Written from this project's page and its Assessment Report and Instrument of Consent on the NSW Planning Portal, on 19 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it
A 29,034 m² warehouse at Aldington Road, Kemps Creek
The project is a warehouse and distribution centre with offices, car parking, hardstand, landscaping and signage on Lot K of the 200 Aldington Road Industrial Estate, Kemps Creek, in the Penrith area. It has a total gross floor area of 29,034 m² and would be up to 14.6 m high, on a site of 62,123 m². It would operate 24 hours a day, 7 days a week. A linked modification changes the estate's approved layout. The cost and job figures are unclear in the text, so none are given.
The environmental impact statement (EIS) was exhibited from 4 Jul 2025 to 4 Aug 2025. Two submissions were received, both comments, from an organisation and a public authority. The department's assessment recommended approval. A director of the department, as the Minister's delegate, approved it on 11 Dec 2025, with conditions. Next, the proponent must meet those conditions, including limits on the roads trucks may use.
- Gross floor area
- 29,034 m²Assessment Report
- Maximum building height
- 14.6 mAssessment Report
- Site area
- 62,123 m²Assessment Report
The department's description
Construction and operation of a warehouse and distribution centre with ancillary office space, car parking, hardstand, landscaping and signage within the 200 Aldington Road Industrial Estate.
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0
Submissions
What the public, organisations and public authorities said, counted by where they stood.
2 submissions: 1 from organisations and 1 from public authorities
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal
Modifications
1 change to the project after its decision, each assessed as a case of its own, newest first.
200 Aldington Road Industrial Estate (Lot K)-Mod-1SSD-80264236-Mod-1
Minor design refinements to the approved Lot K warehouse development.
Its 11 documents
11 documents in 5 folders, each on the NSW Planning Portal
Modification Application1
Agency Advice5
Additional Information2
Determination2
Consolidated Consent1
Documents
By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.
86 documents in 12 folders, each on the NSW Planning Portal
Early Consultation3
Notice of Exhibition1
Request for SEARs1
EIS36
- Appendix A Secretarys Environmental Assessment Requirements
- Appendix AA Social and Economic Assessment
- Appendix BB Waste statement
- Appendix C Public Authority Responses
- Appendix CC Waste Management Plan
- Appendix DD - Sustainability Report
- Appendix E Consolidated Mitigation Measures
- Appendix EE Infrastructure and Utilities
- Appendix F Architectural drawings and design statement
- Appendix FF Building Code of Australia and Access
- Appendix G Landscape plan
- Appendix GG Fire safety strategy
- Appendix H - Statutory and MRP DCP compliance
- Appendix HH CPTED
- Appendix I Aboriginal Cultural Heritage Assessment
- Appendix J Dangerous goods report
- Appendix K EPBC Act Protected Matters Search
- Appendix L Community Engagement Records
- Appendix M Transport statement
- Appendix N Transport impact assessment
- Appendix O Noise impact assessment
- Appendix P Construction Noise and Vibration Impact
- Appendix Q Air Quality Impact Assessment
- Appendix R Construction environmental management plan
- Appendix S Geotechnical and Groundwater Assessment
- Appendix T Civil Works Package
- Appendix U Stormwater Management report
- Appendix V Bushfire Protection Assessment
- Appendix W Historical Heritage
- Appendix X Visual Impact Assessment
- Appendix Y Reslience and hazards
- Appendix Z Aviation safeguarding
- Application_20250620052822
- Lot K - Embodied Emissions Materials Form
- Lot K Warehouse and Modification of SSD_EIS_final 1_2
- MUS008-03-19-609 200A MOD 5 Stage 1, 2 and 3
Response to Submissions4
Agency Advice16
Additional Information3
Determination3
Management Plans and Strategies13
- 260224 - Approval of Plan Strategy or Study
- Approval of 200 Aldington Road Industrial Estate - CNVMP
- Approval of 200 Aldington Road Industrial Estate - CTMP
- B37 Lot K Signage Strategy
- B37 Lot K Signage Strategy - DPHI Approval 200226
- PA24 Approval Letter
- PA24 Revised ESCP
- SSD-80264236 (Lot K) Appendix B - ESCP
- SSD-80264236 (Lot K) Appendix C - CNVMP
- SSD-80264236 (Lot K) Appendix D - CAQMP
- SSD-80264236 (Lot K) Appendix E - C and C Strategy
- SSD-80264236 (Lot K) Appendix F - Unexpected Finds Protocol
- SSD-80264236 CTMP_R11
Reports1
What's near it
Where it is
- Suburb
- Kemps Creek
- Council area
- Penrith
Source ABS suburbs and localities and local government areas (ASGS 2021), CC BY 4.0
Other State projects near it
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0; straight-line distance
Nearest schools
Source NSW Department of Education, CC BY; straight-line distance
Nearest hospitals
Source AIHW MyHospitals, CC BY 4.0; straight-line distance
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project
Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.