Yarrabin (Phoenix) Pumped Hydro

An 810 MW pumped hydro project at Yarrabin

Under way: at prepare eisEnergy: batteriesRegional scale

Where it is in the process

At prepare eis

  1. SEARs (done)
  2. Prepare EIS (current stage)
  3. Exhibition (to come)
  4. Collate Submissions (to come)
  5. Response to Submissions (to come)
  6. Assessment (to come)
  7. Recommendation (to come)
  8. Determination (to come)

What it proposes

AI summary. Written from this project's page and its Scoping Report on the NSW Planning Portal, on 19 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

An 810 MW pumped hydro project at Yarrabin

The proponent proposes an 810 MW / 9,720 MWh pumped hydro energy storage and generation project at 1195 Endacott Road, Yarrabin, mostly in the Dubbo Regional Council area with a small part in Mid-Western Regional. It would have upper and lower reservoirs about 330 m apart in height, joined by a 2.85 km tunnel to a powerhouse with three pump-turbine units. A new 330 kV transmission line would link it to the grid. First filling would need about 16.2 GL of water from Lake Burrendong. No capital investment or job numbers are stated.

The case is at the stage where the proponent prepares an environmental impact statement (EIS). A scoping report was lodged in June 2023 and the Secretary's environmental assessment requirements (SEARs) have been issued. Next, the proponent submits the EIS, which is exhibited so the public can make submissions. No submissions have been received yet.

Generating capacity
810 MWPortal page
Energy storage
9,720 MWhPortal page
Height difference between reservoirs
330 mScoping Report
Tunnel length
2.85 kmScoping Report
Water for first filling
16.2 GLScoping Report
Transmission line voltage
330 kVScoping Report

The department's description

Development of a 810 MW / 9,720 MWh pumped hydro energy storage and generation project, grid connection and ancillary infrastructure.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 19 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.