State significant development

Uungula Wind Farm

Decided: approved on 7 May 2021Energy: wind

Where it is in the process

Approved on 7 May 2021

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination7 May 2021 (done)
  9. Approved7 May 2021

What it proposes

The department's description

Development of a wind farm with up to 93 wind turbines, with energy storage and associated infrastructure.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

64 submissions: 30 from the public, 7 from organisations and 27 from public authorities

Object16
Support18
Comment30

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

4 changes to the project after its decision, each assessed as a case of its own, newest first.

Uungula Wind MOD 4 - On-site containment cellSSD-6687-Mod-4

Under way: at prepare mod report

On-site encapsulation of excavated natural material containing naturally occurring asbestos.

Its page on the Planning Portal

MOD 3 - Minor additional road upgradesSSD-6687-Mod-3

Decided: approved on 4 Sep 2025 by the department (director)

Additional road upgrades along the transport route

Its 8 documents

8 documents in 5 folders, each on the NSW Planning Portal

Modification Application2

See the 2 documents on the Planning Portal

Agency Advice2

See the 2 documents on the Planning Portal

Additional Information1

See the document on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

MOD 2 - Update to Subdivision PlansSSD-6687-Mod-2

Decided: approved on 2 Dec 2022 by the department (director)

To correct errors within the subdivision plans.

Its 5 documents

5 documents in 4 folders, each on the NSW Planning Portal

Modification Application1

See the document on the Planning Portal

Additional Information1

See the document on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

MOD 1 - Turbine Removal and Access Track AmendmentsSSD-6687-Mod-1

Decided: approved on 21 Apr 2022 by the department (director)

- Removal of four turbines and four waterway crossings - Reduction in access track length and clearing required

Its 4 documents

4 documents in 3 folders, each on the NSW Planning Portal

Modification Application1

See the document on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.