On the map
State significant development

Yanco Battery Energy Storage System

Decided: approved on 2 Oct 2025Energy: batteriesDistrict scale

Where it is in the process

Approved on 2 Oct 2025

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination2 Oct 2025 (done)
  9. Approved2 Oct 2025

What it proposes

The department's description

Development of a 250 MW / 1100 MWh battery energy storage system and associated infrastructure and connection works

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

66 submissions: 58 from the public and 8 from organisations

Object64
Support1
Comment1

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

1 change to the project after its decision, each assessed as a case of its own, newest first.

Yanco Battery Energy Storage System - Modification 1SSD-67478479-Mod-1

Decided: approved on 27 May 2026 by the department (director)

Minor changes to the project layout.

Its 16 documents

16 documents in 5 folders, each on the NSW Planning Portal

Modification Application3

See the 3 documents on the Planning Portal

Agency Advice5

See the 5 documents on the Planning Portal

Additional Information5

See the 5 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project