Decided: approved on 4 Oct 2005Other

Where it is in the process

Approved on 4 Oct 2005

  1. Prepare Scoping Report (done)
  2. SEARs (done)
  3. Prepare EIS (done)
  4. Exhibition (done)
  5. Collate Submissions (done)
  6. Response to Submissions (done)
  7. Assessment (done)
  8. Recommendation (done)
  9. Determination4 Oct 2005 (done)
  10. Approved4 Oct 2005

What it proposes

The portal gives no description.

Modifications

2 changes to the project after its decision, each assessed as a case of its own, newest first.

Mod 3 - Increase the number of turbinesDA250-10-2004-Mod-3

Decided: approved on 29 Oct 2010 by Dir(MIA)

Its 38 documents

Its page on the Planning Portal

Mod 1 - Reduce the number of TurbinesDA250-10-2004-Mod-1

Decided: approved on 12 May 2010 by the department (director)

Its 39 documents

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.