A 380,000 tonne a year energy-from-waste plant at Woodlawn

Under way: at response to submissionsEnergy: otherNeighbourhood scale

Where it is in the process

At response to submissions

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (current stage)
  6. Assessment (to come)
  7. Recommendation (to come)
  8. Determination (to come)

What it proposes

AI summary. Written from this project's page and its Woodlawn ARC Environmental Impact Statement on the NSW Planning Portal, on 19 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

A 380,000 tonne a year energy-from-waste plant at Woodlawn

The proponent proposes to build and operate an energy recovery facility at the Woodlawn Eco Precinct, 619 Collector Road, Tarago, in the Goulburn Mulwaree area. It would thermally treat up to 380,000 tonnes of residual waste a year that would otherwise go to landfill, and generate about 30 MW of electricity. The waste would be diverted from waste already approved to arrive by rail, so no extra waste transport is proposed. The works would disturb 38.4 ha. No capital investment or job numbers are stated.

The environmental impact statement (EIS), dated October 2022, was exhibited and drew 627 submissions: 619 objecting, 3 supporting and 5 commenting. The case is now at the response to submissions stage, where the proponent answers the submissions and prepares an amendment report. The department then assesses the project and decides, or refers it for decision.

Waste treated
380,000 tonnes a yearPortal page
Electricity generation capacity
30 MWPortal page
Area disturbed by the project
38.4 haWoodlawn ARC Environmental Impact Statement
Public submissions
627 submissionsPortal page
Submissions objecting
619 submissionsPortal page

The department's description

Construction & operation of an energy recovery facility with a capacity to thermally treat up to 380,000 tpa of residual municipal solid waste and commercial & industrial waste and to generate ~30 MW of electrical energy.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

627 submissions: 593 from the public, 29 from organisations and 5 from public authorities

Object619
Support3
Comment5

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

82 documents in 7 folders, each on the NSW Planning Portal

Notice of Exhibition2
Request for SEARs1
SEARs3
EIS38
Response to Submissions3
Agency Advice32
Amendments3

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.