Woodlawn Advanced Energy Recovery Centre
A 380,000 tonne a year energy-from-waste plant at Woodlawn
Where it is in the process
At response to submissions
What it proposes
AI summary. Written from this project's page and its Woodlawn ARC Environmental Impact Statement on the NSW Planning Portal, on 19 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it
A 380,000 tonne a year energy-from-waste plant at Woodlawn
The proponent proposes to build and operate an energy recovery facility at the Woodlawn Eco Precinct, 619 Collector Road, Tarago, in the Goulburn Mulwaree area. It would thermally treat up to 380,000 tonnes of residual waste a year that would otherwise go to landfill, and generate about 30 MW of electricity. The waste would be diverted from waste already approved to arrive by rail, so no extra waste transport is proposed. The works would disturb 38.4 ha. No capital investment or job numbers are stated.
The environmental impact statement (EIS), dated October 2022, was exhibited and drew 627 submissions: 619 objecting, 3 supporting and 5 commenting. The case is now at the response to submissions stage, where the proponent answers the submissions and prepares an amendment report. The department then assesses the project and decides, or refers it for decision.
- Waste treated
- 380,000 tonnes a yearPortal page
- Electricity generation capacity
- 30 MWPortal page
- Area disturbed by the project
- 38.4 haWoodlawn ARC Environmental Impact Statement
- Public submissions
- 627 submissionsPortal page
- Submissions objecting
- 619 submissionsPortal page
The department's description
Construction & operation of an energy recovery facility with a capacity to thermally treat up to 380,000 tpa of residual municipal solid waste and commercial & industrial waste and to generate ~30 MW of electrical energy.
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0
Submissions
What the public, organisations and public authorities said, counted by where they stood.
627 submissions: 593 from the public, 29 from organisations and 5 from public authorities
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal
Documents
By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.
82 documents in 7 folders, each on the NSW Planning Portal
Notice of Exhibition2
Request for SEARs1
SEARs3
EIS38
- Appendix A - SEARs Compliance Table
- Appendix AA - Historical archaeological assessment
- Appendix B - Consolidated consents
- Appendix BB - Landscape and visual impact assessment
- Appendix C - Woodlawn ARC Architectural Design Report
- Appendix CC - Social impact assessment
- Appendix D - Woodlawn ARC Process Overview
- Appendix DD - Economic assessment
- Appendix E - Ash_Management_Study
- Appendix EE - Preliminary hazard assessment
- Appendix F - Woodlawn Encapsulation Cell Design
- Appendix FF - Fire safety study
- Appendix G - Waste acceptance protocol
- Appendix GG - Operational data Staffordshire ERF
- Appendix H - Woodlawn ARC Commissioning Outline Plan
- Appendix I (i) - Waste Feedstock Analysis
- Appendix I (ii) - Chlorine Content Analysis
- Appendix J - Statutory Compliance Table
- Appendix K - Project engagement
- Appendix L(i) - Woodlawn ARC BAT Assessment
- Appendix L(ii) - Woodlawn ARC Reference Facility
- Appendix M - Mitigation Measures Summary Table
- Appendix N - Transmission line analysis
- Appendix O - Air quality impact assessment
- Appendix P - Human health risk assessment
- Appendix Q - Greenhouse gas impact assessment
- Appendix R - Life cycle analysis
- Appendix S - Noise and vibration assessment
- Appendix T - Traffic impact assessment
- Appendix U - Groundwater impact assessment
- Appendix V - Surface water impact assessment
- Appendix W - Preliminary site investigation
- Appendix X - Bushfire protection assessment
- Appendix Y - Biodiversity development assessment report
- Appendix Z - ACHAR
- Application_20221012010553
- Woodlawn ARC CIV
- Woodlawn ARC Environmental Impact Statement
Response to Submissions3
Agency Advice32
- Advice on EIS - Aboriginal Heritage
- Advice on EIS - BCD
- Advice on EIS - CASA
- Advice on EIS - Crown Lands
- Advice on EIS - DPE Water
- Advice on EIS - DPI Agriculture
- Advice on EIS - DPI Fisheries
- Advice on EIS - EPA
- Advice on EIS - FRNSW
- Advice on EIS - Goulburn Mulwaree Council
- Advice on EIS - Heritage NSW
- Advice on EIS - NSW Health
- Advice on EIS - RFS
- Advice on EIS - Regional NSW - MEG
- Advice on EIS - Safework
- Advice on EIS - TfNSW
- Advice on EIS - Upper Lachlan Shire Council
- Advice on EIS - WaterNSW
- Advice on SEARS - FRNSW
- Advice on SEARs - BCD
- Advice on SEARs - Council
- Advice on SEARs - DPIE Water & NRAR
- Advice on SEARs - EPA
- Advice on SEARs - HCNSW
- Advice on SEARs - HNSW ACH
- Advice on SEARs - NSW Health
- Advice on SEARs - RFS
- Advice on SEARs - TfNSW
- Advice on SEARs - WaterNSW
- Advice on SEARs - WaterNSW
- EPA Advice on EIS - Appendix 1
- Objection on EIS - Goulburn Mulwaree Council
What's near it
Where it is
- Suburb
- Tarago
- Council area
- Goulburn Mulwaree
Source ABS suburbs and localities and local government areas (ASGS 2021), CC BY 4.0
Other State projects near it
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0; straight-line distance
Nearest schools
Source NSW Department of Education, CC BY; straight-line distance
Nearest hospitals
Source AIHW MyHospitals, CC BY 4.0; straight-line distance
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project
Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.