On the map
State significant development

Wongalea Battery Energy Storage System

A 300 MW battery on Grafton Road, Armidale

Under way: at exhibitionEnergy: batteriesDistrict scale

Where it is in the process

At exhibition, since 6 Nov 2026

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition6 Nov 2026 (current stage)
  4. Collate Submissions (to come)
  5. Response to Submissions (to come)
  6. Assessment (to come)
  7. Recommendation (to come)
  8. Determination (to come)

Open for comment until 4 Dec 2026. Anyone can make a submission on its page on the Planning Portal.

What it proposes

AI summary. Written from this project's page and its Wongalea BESS Environmental Impact Statement on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

A 300 MW battery on Grafton Road, Armidale

The proponent proposes a battery energy storage system with a capacity of up to 300 MW and 1,200 MWh, mainly at 475 Grafton Road, about 5 km east of Armidale, in the Armidale Regional Council area. It would connect to the existing Armidale substation by an underground 132 kV cable. It would also include batteries in containers, transformers, inverters, a control building, internal tracks and vegetation screening. Up to 110 full time equivalent staff would work on site each day at peak construction, and 2 to 5 during operation. No capital investment is stated.

The environmental impact statement (EIS) is on exhibition from 6 Nov 2026 to 4 Dec 2026, and no submissions have been made yet. Next, the proponent responds to the submissions and may amend the project. The department then assesses it and a decision is made. The Independent Planning Commission decides if there are 50 or more objections or the council objects; otherwise the Minister does.

Battery power capacity
300 MWWongalea BESS Environmental Impact Statement
Battery storage capacity
1,200 MWhWongalea BESS Environmental Impact Statement
Peak construction staff per day
110 full time equivalent staffWongalea BESS Environmental Impact Statement
Transmission connection voltage
132 kVWongalea BESS Environmental Impact Statement

The department's description

Construction, operation, and decommissioning of a Battery Energy Storage System with a capacity of approximately 300 MW/1200 MWh, and ancillary infrastructure.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

38 documents in 5 folders, each on the NSW Planning Portal

Notice of Exhibition1
Request for SEARs10
SEARs1
EIS18
Agency Advice8

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.