Armidale Battery Energy Storage System

A 150 MW battery on Eathorpe Road, Armidale

Decided: approved on 5 Dec 2025Energy: batteriesDistrict scale

Where it is in the process

Approved on 5 Dec 2025

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination5 Dec 2025 (done)
  9. Approved5 Dec 2025

What it proposes

AI summary. Written from this project's page and its Assessment Report and Instrument of Consent on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

A 150 MW battery on Eathorpe Road, Armidale

The project is a battery energy storage system with a capacity of up to 150 MW and 437 MWh, about 5 km east of Armidale in the Armidale Regional Council area. It includes a substation, a switch room, a control room and a 264 m underground line to the existing Armidale substation. It would be built over about 24 months on a 13.3 ha site. The estimated development cost is $209 million, with up to 100 construction jobs and 2 operational jobs.

The environmental impact statement (EIS) was exhibited from 27 Oct 2023 to 23 Nov 2023. It drew 32 submissions: 31 objecting and 1 commenting. The proponent amended the project twice, in February 2025 and July 2025. The department's assessment report of December 2025 found it approvable, subject to conditions. The department's Executive Director approved it on 5 Dec 2025 as the Minister's delegate. Next, the proponent must meet the consent's conditions before construction.

Capital investment
$209MAssessment Report
Battery power capacity
150 MWAssessment Report
Battery storage capacity
437 MWhAssessment Report
Construction jobs
100 jobsAssessment Report
Operational jobs
2 jobsAssessment Report
Underground transmission connection
264 mAssessment Report
Site area
13.3 haAssessment Report
Development footprint
5.65 haAssessment Report

The department's description

Development of a 150 MW battery energy storage facility with associated infrastructure

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

32 submissions: 30 from the public and 2 from organisations

Object31
Support0
Comment1

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

100 documents in 9 folders, each on the NSW Planning Portal

Notice of Exhibition1
Request for SEARs1
SEARs1
EIS11
Response to Submissions8
Agency Advice43
Amendments14
Additional Information18
Determination3