Armidale Battery Energy Storage System
A 150 MW battery on Eathorpe Road, Armidale
Where it is in the process
Approved on 5 Dec 2025
What it proposes
AI summary. Written from this project's page and its Assessment Report and Instrument of Consent on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it
A 150 MW battery on Eathorpe Road, Armidale
The project is a battery energy storage system with a capacity of up to 150 MW and 437 MWh, about 5 km east of Armidale in the Armidale Regional Council area. It includes a substation, a switch room, a control room and a 264 m underground line to the existing Armidale substation. It would be built over about 24 months on a 13.3 ha site. The estimated development cost is $209 million, with up to 100 construction jobs and 2 operational jobs.
The environmental impact statement (EIS) was exhibited from 27 Oct 2023 to 23 Nov 2023. It drew 32 submissions: 31 objecting and 1 commenting. The proponent amended the project twice, in February 2025 and July 2025. The department's assessment report of December 2025 found it approvable, subject to conditions. The department's Executive Director approved it on 5 Dec 2025 as the Minister's delegate. Next, the proponent must meet the consent's conditions before construction.
- Capital investment
- $209MAssessment Report
- Battery power capacity
- 150 MWAssessment Report
- Battery storage capacity
- 437 MWhAssessment Report
- Construction jobs
- 100 jobsAssessment Report
- Operational jobs
- 2 jobsAssessment Report
- Underground transmission connection
- 264 mAssessment Report
- Site area
- 13.3 haAssessment Report
- Development footprint
- 5.65 haAssessment Report
The department's description
Development of a 150 MW battery energy storage facility with associated infrastructure
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0
Submissions
What the public, organisations and public authorities said, counted by where they stood.
32 submissions: 30 from the public and 2 from organisations
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal
Documents
By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.
100 documents in 9 folders, each on the NSW Planning Portal
Notice of Exhibition1
Request for SEARs1
SEARs1
EIS11
- EIS Appendix D - ACHAR
- EIS Appendix E - BDAR
- EIS Appendix F - LUCRA
- EIS Appendix G - Preliminary Site Contamination Assessment
- EIS Appendix H - Flood Impact Assessment
- EIS Appendix I - Traffic Impact Assessment
- EIS Appendix J - Noise Impact Assessment
- EIS Appendix K - Visual Impact Assessment
- EIS Appendix L - Preliminary Hazard Assessment
- EIS Application Form
- Environmental Impact Statement
Response to Submissions8
- RTS Attachment C - Biodiversity Development Assessment Report
- RTS Attachment D - Aboriginal Cultural Heritage Assessment
- RTS Attachment E - Traffic Impact Assessment
- RTS Attachment F - Preliminary Hazard Assessment
- RTS Attachment G - Preliminary Accommod and Employ Strategy
- RTS Attachment H - Landscape and Visual Impact Assessment
- Request RTS Letter
- Submissions Report
Agency Advice43
- AR 1 Advice - DPIRD Resources
- AR 2 Advice - Armidale Regional Council
- AR 2 Advice - HNSW ACH
- AR 2 Advice - NSW DCCEEW CPHR
- AR1 Advice - RFS
- AR2 Advice - Crown Lands
- AR2 Advice - DPHI Hazards
- AR2 Advice - TfNSW
- EIS Advice - Armidale Regional Council
- EIS Advice - Crown Lands
- EIS Advice - DCCEEW CPHR
- EIS Advice - DPE Water
- EIS Advice - DPI Agriculture
- EIS Advice - FRNSW
- EIS Advice - Heritage
- EIS Advice - Heritage NSW ACH
- EIS Advice - MEG
- EIS Advice - RFS
- EIS Advice - Subsidence Advisory
- EIS Advice - TfNSW
- RTS & AR 1 Advice - DPHI Hazards
- RTS Advice - DPIRD Resources
- RTS Advice - RFS
- RTS and AR 1 Advice - Armidale Regional Council
- RTS and AR 1 Advice - Crown Lands
- RTS and AR 1 Advice - DCCEEW Water Group
- RTS and AR 1 Advice - DPIRD Agriculture
- RTS and AR 1 Advice - EnergyCo
- RTS and AR 1 Advice - FRNSW
- RTS and AR 1 Advice - HNSW
- RTS and AR 1 Advice - HNSW ACH
- RTS and AR 1 Advice - NSW DCCEEW CPHR
- RTS and AR 1 Advice - TfNSW
- SEARs Advice - Armidale Regional Council
- SEARs Advice - DCCEEW CPHR
- SEARs Advice - DPE Water
- SEARs Advice - DPI Agriculture
- SEARs Advice - FRNSW
- SEARs Advice - HNSW ACH
- SEARs Advice - Heritage NSW
- SEARs Advice - MEG
- SEARs Advice - NSW EPA
- SEARs Advice - TfNSW
Amendments14
- AR 1 (February 2025) - Appendix D - Biodiversity Development Assessment Report
- AR 1 (February 2025) - Appendix E - Landscape and Visual
- AR 1 (February 2025) - Appendix F - Traffic Impact Assessment
- AR 1 (February 2025) - Appendix G - Operational Noise Assessment Report
- AR 1 (February 2025) - Appendix H - Aboriginal Cultural Heritage Assessment Report
- AR 1 (February 2025) - Appendix I - Preliminary Hazard Assessment
- AR 1 (February 2025) - Appendix J - Preliminary Accommodation
- AR 2 (July 2025) - Appendix C - Addendum Traffic Impact Assessment - Part 1
- AR 2 (July 2025) - Appendix C - Addendum Traffic Impact Assessment - Part 2
- AR 2 (July 2025) - Appendix C - Addendum Traffic Impact Assessment - Part 3
- Amendment Acceptance Letter 1 (July 2025)
- Amendment Acceptance Letter 2 (July 2025)
- Amendment Report 1 (February 2025)
- Amendment Report 2 (July 2025)
Additional Information18
- 1.1 Request for Advice on RTS - CPHR (23 March 2025)
- 1.2 Response to CPHR Advice - Final BDAR (4 April 2025)
- 1.3 Advice on RFI Response - CPHR (14 May 2025)
- 2.1 Compiled Agency Request for Advice on RTS
- 2.2 Response on Agency Advice (18 June 2025)
- 2.3 Compiled Agency Advice on Response
- 3.1 Request for Advice on RTS - TfNSW (26 March 2025)
- 3.2 Response to TfNSW Advice - Addendum TIA (11 June 2025)
- 3.3 Advice on RFI Response - TfNSW (4 July 2025)
- 3.4 Advice on AR2 and Updated TIA - TfNSW (18 August 2025)
- 4.1 Request for Additional Information (1 September 2025)
- 4.2 Response to RFI (28 October 2025)
- 5.1 Request for Additional Information (20 November 2025)
- 5.2 Response to RFI (24 November 2025)
- Addendum TIA Part 1 (October 2025)
- Addendum TIA Part 2 (October 2025)
- Addendum TIA Part 3 (October 2025)
- Change of Applicant Notification
Determination3
What's near it
Where it is
- Suburb
- Armidale
- Council area
- Armidale Regional
Source ABS suburbs and localities and local government areas (ASGS 2021), CC BY 4.0
Other State projects near it
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0; straight-line distance
Nearest schools
Source NSW Department of Education, CC BY; straight-line distance
Nearest hospitals
Source AIHW MyHospitals, CC BY 4.0; straight-line distance
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project
Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.