On the map
State significant development

Wagga Wagga Hospital Redevelopment - Stage 3

Decided: approved on 18 Dec 2018Health

Where it is in the process

Approved on 18 Dec 2018

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination18 Dec 2018 (done)
  9. Approved18 Dec 2018

What it proposes

The portal gives no description.

Submissions

What the public, organisations and public authorities said, counted by where they stood.

8 submissions: 1 from the public and 7 from organisations

Object0
Support0
Comment8

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

5 changes to the project after its decision, each assessed as a case of its own, newest first.

Wagga Hospital Stg 3 MOD 5 - Changes to parkingSSD-9033-Mod-5

Decided: approved on 9 Jun 2021 by the department (director)

Amendments to car parking layout and minor landscaping works.

Its 13 documents

13 documents in 4 folders, each on the NSW Planning Portal

Modification Application4

See the 4 documents on the Planning Portal

Additional Information5

See the 5 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Wagga Hospital Stg 3 MOD 4 - Generator relocationSSD-9033-Mod-4

Decided: approved on 8 Jul 2020 by the department (director)

Relocation of generator.

Its 10 documents

10 documents in 4 folders, each on the NSW Planning Portal

Modification Application5

See the 5 documents on the Planning Portal

Additional Information1

See the document on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Wagga Hospital Stg 3 MOD 3 - Staging conditionsSSD-9033-Mod-3

Decided: approved on 19 Dec 2019 by the department (director)

Insertion of staging conditions in consent.

Its 4 documents

4 documents in 3 folders, each on the NSW Planning Portal

Modification Application1

See the document on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Wagga Hospital Stg 3 MOD 2 - Basement carparkSSD-9033-Mod-2

Decided: approved on 25 Aug 2019 by the department (director)

Extension of basement carpark to accommodate 32 additional spaces.

Its 15 documents

15 documents in 3 folders, each on the NSW Planning Portal

Modification Application11

See the 11 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Wagga Wagga Hospital Stage 3 MOD 1 - ContaminationSSD-9033-Mod-1

Decided: approved on 12 Jun 2019 by the department (director)

Modification to Condition B7 - Unexpected Contamination Procedure to allow for onsite management of contaminated materials.

Its 1 documents

1 document in 1 folder, each on the NSW Planning Portal

Early Consultation1

See the document on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.