Decided: approved on 9 Mar 2012Waste

Where it is in the process

Approved on 9 Mar 2012

  1. Prepare Scoping Report (done)
  2. SEARs (done)
  3. Prepare EIS (done)
  4. Exhibition (done)
  5. Collate Submissions (done)
  6. Response to Submissions (done)
  7. Assessment (done)
  8. Recommendation (done)
  9. Determination9 Mar 2012 (done)
  10. Approved9 Mar 2012

What it proposes

The portal gives no description.

Submissions

What the public, organisations and public authorities said, counted by where they stood.

1 submission: 1 from the public

Object0
Support0
Comment1

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

1 change to the project after its decision, each assessed as a case of its own, newest first.

Mod 1 - Groundwater TreatmentMP10_0040-Mod-1

Decided: approved with conditions on 28 Feb 2013 by the department (executive director)

Its 9 documents

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.