On the map
State significant development

Tomago Potliner Facility

Decided: approved on 7 Aug 2009Other

Where it is in the process

Approved on 7 Aug 2009

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Assessment (done)
  6. Recommendation (done)
  7. Determination7 Aug 2009 (done)
  8. Approved7 Aug 2009

What it proposes

The portal gives no description.

Modifications

4 changes to the project after its decision, each assessed as a case of its own, newest first.

Tomago Potliner Facility MOD 3 - Process ChangesMP06_0050-Mod-3

Decided: approved on 11 Apr 2025 by the department (executive director) · 1 submission

Modification to thermal treatment process to include steam injection into the thermal treatment kiln.

Its 17 documents

17 documents in 6 folders, each on the NSW Planning Portal

Notice of Exhibition1

See the document on the Planning Portal

Modification Application2

See the 2 documents on the Planning Portal

Response to Submissions3

See the 3 documents on the Planning Portal

Agency Advice8

See the 8 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Tomago Potliner Facility MOD 4 - Cleaning StationMP06_0050-Mod-4

Decided: approved on 14 Nov 2024 by the department (team leader)

Construction and operation of a container cleaning station , and use an existing container hardstand area as a transit area for temporary storage of SPL containers.

Its 14 documents

14 documents in 5 folders, each on the NSW Planning Portal

Modification Application1

See the document on the Planning Portal

Agency Advice5

See the 5 documents on the Planning Portal

Additional Information5

See the 5 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Tomago Potliner Facility MOD 2 - Increase CapacityMP06_0050-Mod-2

Decided: approved on 22 Aug 2019 by the department (director) · 1 submission

/

Its 14 documents

Its page on the Planning Portal

Tomago Potliner Facility MOD 1 - Amend Condition 5MP06_0050-Mod-1

Decided: approved on 16 Nov 2016 by the department (director)

/

Its 7 documents

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.