Tomago Battery Energy Storage System
Where it is in the process
Approved on 8 Nov 2024
What it proposes
The department's description
Development of a 500 MW / 2000 MWh battery energy storage system and associated infrastructure including grid connection.
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0
Submissions
What the public, organisations and public authorities said, counted by where they stood.
24 submissions: 18 from the public, 5 from organisations and 1 from public authorities
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal
Documents
By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.
105 documents in 12 folders, each on the NSW Planning Portal
Notice of Exhibition1
Request for SEARs1
Response to Submissions2
Agency Advice37
Additional Information9
Determination3
Management Plans and Strategies18
Independent Reviews and Audits2
Notifications1
Other Documents19
What's near it
Where it is
- Suburb
- Tomago
- Council area
- Port Stephens
Source ABS suburbs and localities and local government areas (ASGS 2021), CC BY 4.0
Other State projects near it
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0; straight-line distance
Nearest schools
Source NSW Department of Education, CC BY; straight-line distance
Nearest hospitals
Source AIHW MyHospitals, CC BY 4.0; straight-line distance
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project
Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.