On the map
State significant infrastructure

Newcastle Power Station

Decided: approved on 15 Mar 2021Energy: otherDistrict scale

Where it is in the process

Approved on 15 Mar 2021

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination15 Mar 2021 (done)
  9. Approved15 Mar 2021

What it proposes

The department's description

A Critical State Significant Infrastructure application, involving construction and operation of a 250 megawatt (MW) gas fired power station and ancillary infrastructure.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

28 submissions: 5 from the public, 9 from organisations and 14 from public authorities

Object5
Support2
Comment21

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.