On the map
State significant development

Project Silverback Oakdale East Industrial Estate

Two warehouses at Oakdale East Industrial Estate, Horsley Park

Under way: at assessmentIndustry and warehousesDistrict scale

Where it is in the process

At assessment

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (current stage)
  7. Recommendation (to come)
  8. Determination (to come)

What it proposes

AI summary. Written from this project's page and its EIS on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

Two warehouses at Oakdale East Industrial Estate, Horsley Park

The proponent proposes two 24-hour warehouse and distribution buildings on Lot 109 in DP 1293112, part of the Oakdale East Industrial Estate at Horsley Park, in the Fairfield City area. Building 2A would have about 18,110 m² of floor area and a ridge height of 14.6 m. Building 2B, an automated mail and parcel sorting facility, would have about 142,157 m² across two levels and a ridge height of 25.0 m. The site covers about 30.5 ha. About 550,000 m³ of fill would be imported. It also seeks changes to the estate's concept approval. No capital investment is stated.

The environmental impact statement (EIS) is dated July 2026, following the Secretary's requirements issued on 8 May 2026. The case drew 4 submissions: 1 supporting and 3 commenting. The proponent has responded to them. The department is now assessing the project. Next come its assessment report and a decision.

Building 2A floor area
18,110 m²EIS
Building 2A ridge height
14.6 mEIS
Building 2B floor area
142,157 m²EIS
Building 2B ridge height
25 mEIS
Site area
30.5 haEIS
Fill to be imported
550,000 m³EIS

The department's description

1. Amendments to the Concept approval and Stage 2 infrastructure works under SSD-37486043

2. Construction, fit-out and operation of 2 warehouse buildings

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

4 submissions: 2 from the public, 1 from organisations and 1 from public authorities

Object0
Support1
Comment3

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

88 documents in 6 folders, each on the NSW Planning Portal

Early Consultation4
SEARs1
EIS49
Response to Submissions18
Agency Advice14
Additional Information2

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.