On the map
State significant development

Project Atlas Data Centre Eastern Creek

A 500 MVA data centre at 10 Roberts Road, Eastern Creek

Under way: at assessmentData centresDistrict scale

Where it is in the process

At assessment

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (current stage)
  7. Recommendation (to come)
  8. Determination (to come)

What it proposes

AI summary. Written from this project's page and its EIS - 10 Roberts Road, Eastern Creek on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

A 500 MVA data centre at 10 Roberts Road, Eastern Creek

The proponent proposes to demolish the existing buildings at 10 Roberts Road, Eastern Creek, in the Blacktown council area, and build and run a 500 MVA data centre. The project also includes off-site enabling infrastructure, such as an underground high-voltage cable route. No capital investment, floor area, building height or job numbers are stated.

The proponent's environmental impact statement (EIS) is dated May 2026. The case has drawn 21 submissions: 17 objecting, 2 supporting and 2 commenting. The proponent has responded to submissions, and agencies have given advice. The department has since asked for more information, and the case is at that stage. Next, the proponent provides the information. The department then finishes its assessment and report, and a decision is made. No decision date is stated.

Data centre capacity
500 MVAPortal page
Public submissions
21 submissionsPortal page
Submissions objecting
17 submissionsPortal page

The department's description

Demolition of existing buildings and construction/operation of a 500MVA data centre at 10 Roberts Road, including offsite enabling infrastructure

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

21 submissions: 18 from the public, 2 from organisations and 1 from public authorities

Object17
Support2
Comment2

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

135 documents in 8 folders, each on the NSW Planning Portal

Early Consultation2
Notice of Exhibition1
Request for SEARs2
SEARs5
EIS45
Response to Submissions57
Agency Advice21
Additional Information2

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.