State significant development

Roberts Road Data Centre

Decided: approved on 14 Jul 2020Industry and warehouses

Where it is in the process

Approved on 14 Jul 2020

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination14 Jul 2020 (done)
  9. Approved14 Jul 2020

What it proposes

The department's description

An expansion to an existing data centre, including associated office space, supporting infrastructure and services, car parking and landscaping.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

9 submissions: 2 from organisations and 7 from public authorities

Object0
Support0
Comment9

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

4 changes to the project after its decision, each assessed as a case of its own, newest first.

Roberts Road DC MOD 4 - Changes to Operational InfrastructureSSD-10330-Mod-4

Under way: at prepare mod report

The modification involves changes to the operational plant and layout of the approved data centre, including additional back-up generators and cooling equipment.

Its 17 documents

17 documents in 1 folder, each on the NSW Planning Portal

Modification Application17

See the 17 documents on the Planning Portal

Its page on the Planning Portal

Roberts Road DC MOD 3 - High-Voltage Plant ModificationSSD-10330-Mod-3

Decided: approved on 8 Sep 2026 by the department (team leader)

– Installation of a new switch room with 11 kV switchgear – Installation of a new (fifth) Transformer – Replacement of the existing Transformer 1 and 2.

Its 16 documents

16 documents in 4 folders, each on the NSW Planning Portal

Modification Application9

See the 9 documents on the Planning Portal

Agency Advice3

See the 3 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Roberts Road DC MOD 2 - Additional back-up generators and diesel storageSSD-10330-Mod-2

Decided: approved on 6 Mar 2026 by the department (team leader)

Modification to the Roberts Road Data Centre to provide additional back-up generators and diesel storage

Its 29 documents

29 documents in 5 folders, each on the NSW Planning Portal

Modification Application9

See the 9 documents on the Planning Portal

Agency Advice6

See the 6 documents on the Planning Portal

Additional Information10

See the 10 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Roberts Road Data Centre MOD 1 - Height IncreaseSSD-10330-Mod-1

Decided: approved on 17 Apr 2024 by the department (team leader)

Additional storey to buildings 5 and 6, including internal layout reconfiguration

Its 19 documents

19 documents in 5 folders, each on the NSW Planning Portal

Modification Application5

See the 5 documents on the Planning Portal

Agency Advice2

See the 2 documents on the Planning Portal

Additional Information8

See the 8 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.