Decided: approved on 23 Jul 2026Data centresRegional scale

Where it is in the process

Approved on 23 Jul 2026

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination23 Jul 2026 (done)
  9. Approved23 Jul 2026

What it proposes

AI summary. Written from this project's page and its Signed - SSD Instrument of Consent and Signed - SSD-SSI Assessment Report on the NSW Planning Portal, on 19 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

A 100 MW data centre at McCredie Road, Guildford West

The project is a data centre at 132 McCredie Road, Guildford West, in the Cumberland area, on about 7.17 ha of industrial land. It has nine data halls over two storeys, a gross floor area of 29,444 m² and a maximum height of 25.77 m. Total power use is 100 MW, with back-up diesel generators and lithium-ion batteries. The estimated development cost is $1.1 billion, with up to 467 construction jobs and 60 operational jobs.

The environmental impact statement (EIS) was exhibited from 9 May 2025 to 6 Jun 2025. The portal counts 4 submissions, all comments, from 2 organisations and 2public authorities. The department's assessment found the project approvable, mainly on noise, air quality and design and visual impact. A director of the department, as the Minister's delegate, approved it on 23 Jul 2026 with conditions. Next, the proponent must meet those conditions before and during construction.

Estimated development cost
$1.11bnSigned - SSD-SSI Assessment Report
Total power consumption
100 MWSigned - SSD-SSI Assessment Report
Construction jobs
467 jobsSigned - SSD-SSI Assessment Report
Operational jobs
60 jobsSigned - SSD-SSI Assessment Report
Maximum building height
25.77 mSigned - SSD-SSI Assessment Report
Gross floor area
29,444 m²Signed - SSD-SSI Assessment Report
Site area
7.17 haSigned - SSD-SSI Assessment Report

The department's description

Construction and operation of a data centre with a load capacity of 100MW comprising of two, three-storey buildings, substations, ancillary office space, car parking, landscaping and demolition works.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

4 submissions: 2 from organisations and 2 from public authorities

Object0
Support0
Comment4

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

110 documents in 8 folders, each on the NSW Planning Portal

Notice of Exhibition1
Request for SEARs2
SEARs2
EIS39
Response to Submissions20
Agency Advice17
Additional Information26
Determination3

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.