On the map
Part 4 development

Smithfield Cogeneration Facility

Decided: approvedEnergy: other

Where it is in the process

Approved

  1. Prepare Scoping Report (done)
  2. SEARs (done)
  3. Prepare EIS (done)
  4. Exhibition (done)
  5. Collate Submissions (done)
  6. Response to Submissions (done)
  7. Assessment (done)
  8. Recommendation (done)
  9. Determination (done)
  10. Approved

What it proposes

The portal gives no description.

Modifications

2 changes to the project after its decision, each assessed as a case of its own, newest first.

Mod 2 - Smithfield Cogeneration FacilityDA94/162-Mod-2

Decided: approved by the department (executive director)

Its page on the Planning Portal

Mod 1 - Smithfield Cogeneration FacilityDA94/162-Mod-1

Decided: approved by the department (director)

Its page on the Planning Portal